EPNG Maintenance Calendar
November 2025
Seg Area
Seg Nbr
Flow Dir
Location
Base Capacity (MDth)
Sat 1
Sun 2
Mon 3
Tue 4
Wed 5
Thu 6
Fri 7
Sat 8
Sun 9
Mon 10
Tue 11
Wed 12
Thu 13
Fri 14
Sat 15
Sun 16
Mon 17
Tue 18
Wed 19
Thu 20
Fri 21
Sat 22
Sun 23
Mon 24
Tue 25
Wed 26
Thu 27
Fri 28
Sat 29
Sun 30
Anadarko
690
F
PLAIN ST
756
213
% Seg Avail
72%
740
B
AMAR N
283
83
158
71%
44%
AMAR S
311
111
186
64%
40%
Lincoln Crossover
640
CAPROCK N
621
71
89%
Line 1903
3000
MOJTHRU
463
117
100%
75%
Mojave Seamless
3040
MOJEAST
195
0
0%
MOJAVE
400
54
87%
North Mainline
200
NORTH ML
2298
284
304
130
233
88%
94%
90%
Permian Virtual Segment
940
CRANEUPT
KEYST ST
781
59
KEYSTAFL
753
30
L2000
611
43
WA2CORN
759
90
613
301321 (IARCOPUC)
56
302803 (DGPMGOLD)
26
50498 (ISALTCRK)
550
267
51%
800925 (DSODALKE)
5
South Mainline
1600
CORN HPW
610
78
CORN LPW
1196
92
CORNL2K
600
34
CORNTRN
146
91
2552
1640
EL PASO
1271
ELPASO C
614
ELPASO E
603
2488
1690
FLOR B
617
FLOR C
606
FLORIDA
1003
2226
1760
LORDS B
605
73
LORDS C
593
25
LORDSBRG
1011
150
2209
66%
65%
1800
BOWIE
CIMARRON
591
DRAGOON
716
1910
96%
68%
67%
1920
ORACLE
601
TOM MIX
588
24
VAIL
675
1864
99%
2160
WENDEN
2221
WENDWST
1578
872
3799
77%
2500
EHRENBRG
2075
301016 (DSCALEHR)
1481
314980 (IBLYTHE)
80
Start Date
End Date
Region
Scheduling Location
Maintenance List
Base Capacity Dthd
Total Reduction Dthd
PLM Reduction Dthd
FMJ Reduction Dthd
Net Dthd
Update
11/01/25
11/03/25
NM
Flagstaff 2A equipment failure repair - FMJ Reduction Dilkon 1A repair
2,298,533
284,783
154,470
130,313
2,013,750
11/04/25
11/06/25
Flagstaff 2A equipment failure repair - FMJ Reduction Dilkon 1A repair Window Rock 6B inspection
304,767
174,454
1,993,766
11/07/25
11/10/25
Flagstaff 2A equipment failure repair - FMJ Reduction Dilkon 1A repair - Completed
-
2,168,220
11/11/25
11/13/25
Flagstaff 2A equipment failure repair - FMJ Reduction Dilkon 1A repair - Completed Window Rock 4A inspection
233,093
102,780
2,065,440
11/14/25
11/30/25
XO
Laguna Station Station equipment failure repair - FMJ Reduction Caprock 2A equipment failure repair - FMJ Reduction
621,000
71,379
549,621
AN
Amarillo 1A equipment failure repair - FMJ Reduction Amarillo 2A equipment failure repair - FMJ Reduction Dimmitt 2A maintenance Dimmitt 3A repair - No additional capacity impact - Informational Only
283,500
83,500
200,000
Amarillo 1A equipment failure repair - FMJ Reduction Amarillo 2A equipment failure repair - FMJ Reduction Dimmitt 2A maintenance Dimmitt 3A repair - No additional capacity impact - Informational Only Dimmitt Station maintenance
158,363
74,863
125,137
311,700
111,700
186,563
110,222
76,341
PR
Plains 3A repair Plains 8A repair Plains 14A repair Plains 15A repair
756,100
213,839
542,261
Keystone 11A repair Keystone 2B repair
781,000
59,330
721,670
753,100
30,770
722,330
11/08/25
Line 1105 pipeline remediation MLV 0 to MLV 1
233,000
302803
Line 1115 pipeline maintenance MLV 0 - Phillips Goldsmith Fuel Delivery (DGPMGOLD) - Customer to zero Dth/d during Line 1115 pipeline maintenance MLV 0 - Rescheduled and revised to Line 6068 pipeline maintenance
26,800
Line 6068 pipeline maintenance - Phillips Goldsmith Fuel Delivery (DGPMGOLD) - Customer to zero Dth/d during Line 6068 pipeline maintenance
11/20/25
301321
Line 3146 pipeline maintenance - MLV 2 to MLV 3 - Arco to Puckett Receipt (IARCOPUC) - Customer to zero Dth/d during Line 3146/1105 pipeline maintenance - MLV 2 to MLV 3
56,970
800925
Line 3146/1105 pipeline maintenance - MLV 2 to MLV 3 - Soda Lake Delivery (DSODALKE) - Customer to zero Dth/d during Line 3146/1105 pipeline maintenance - MLV 2 to MLV 3
5,681
50498
Salt Creek Receipt (ISALTCRK) - Customer limited to 282,716 Dth/d during meter station maintenance
550,000
267,284
282,716
SM
Hueco 3A equipment failure repair - FMJ Reduction Cornudas 1A equipment failure repair - FMJ Reduction
1,196,700
92,950
1,103,750
Lordsburg 2A maintenance
1,011,600
150,126
861,474
11/12/25
Line 1103 pipeline maintenance Wenden to Ehrenberg - Revised Capacity Impact Dth/d
1,578,000
872,035
705,965
2,075,500
301016
Line 1103 pipeline maintenance Wenden to Ehrenberg - 301016 (DSCALEHR) So Cal Ehrenberg Delivery Revised Capacity Impact
1,481,910
314980
Line 1103 pipeline maintenance Wenden to Ehrenberg - Blythe Power Plant Delivery - (IBLYTHE) - Customer currently not impacted during Line 1103 pipeline maintenance Wenden to Ehrenberg - Informational Only
80,000
Gresham Station mechanical failure repair - FMJ Reduction
759,200
90,936
668,264
11/21/25
Gresham Station mechanical failure repair - FMJ Reduction Line 1600 pipeline maintenance El Paso to Lordsburg Line 1600 pipeline remediation El Paso to Florida
613,200
522,264
146,000
11/22/25
Gresham Station mechanical failure repair - FMJ Reduction Line 1600 pipeline maintenance El Paso to Lordsburg - Reduced Outage Duration Line 1600 pipeline remediation El Paso to Florida - Reduced Outage Duration
91,956
54,044
Gresham Station mechanical failure repair - FMJ Reduction - Revised capacity impact during Line 1600 pipeline outages Line 1600 pipeline maintenance El Paso to Lordsburg Line 1600 pipeline remediation El Paso to Florida
Bowie Station maintenance
610,900
78,845
532,055
Line 1600 pipeline maintenance El Paso to Lordsburg Line 1600 pipeline remediation El Paso to Florida Bowie Station maintenance
Line 1600 pipeline maintenance El Paso to Lordsburg - Reduced Outage Duration Line 1600 pipeline remediation El Paso to Florida - Reduced Outage Duration Bowie Station maintenance
Line 1600 pipeline maintenance El Paso to Lordsburg Line 1600 pipeline remediation El Paso to Florida
614,000
Line 1600 pipeline maintenance El Paso to Lordsburg - Reduced Outage Duration Line 1600 pipeline remediation El Paso to Florida - Reduced Outage Duration
617,100
605,300
73,245
603,300
71,245
Bowie Station maintenance Line 1600 pipeline maintenance El Paso to Lordsburg Line 1600 pipeline remediation El Paso to Florida
Bowie Station maintenance Line 1600 pipeline maintenance El Paso to Lordsburg - Reduced Outage Duration Line 1600 pipeline remediation El Paso to Florida - Reduced Outage Duration
11/17/25
11/18/25
Cornudas 2C inspection
611,700
43,783
567,917
Tom Mix 1A inspection
600,800
26,934
573,866
34,474
566,326
593,900
25,973
567,927
34,790
559,110
591,600
25,807
565,793
34,846
556,754
588,500
24,351
564,149
11/05/25
MOJ
Mojave 3A inspection
400,000
54,000
346,000
463,000
117,000
11/09/25
Daggett Station Flow Control Valve Maintenance - Interconnect East Flow Capacity Reduced to Zero Dth/d - Delayed
195,000
11/23/25
Daggett Station Flow Control Valve Maintenance - Interconnect East Flow Capacity Reduced to Zero Dth/d
In addition to planned outages, this report reflects the repairs and maintenance being performed related to Force Majeure events.
Due to the nature of such events, the dates for the associated repairs and maintenance of those events are assumed to extend until the end of the month.
These repairs and maintenance, however, may extend beyond the end of the month including beyond the current year.
More information on these repairs and maintenance will be posted as a Critical Notice under the Notices section of the Informational Postings tab on the EPNG Electronic Bulletin Board.
Your session will expire in . Click OK to renew your session.