EPNG Maintenance Calendar
September 2025
Seg Area
Seg Nbr
Flow Dir
Location
Base Capacity (MDth)
Mon 1
Tue 2
Wed 3
Thu 4
Fri 5
Sat 6
Sun 7
Mon 8
Tue 9
Wed 10
Thu 11
Fri 12
Sat 13
Sun 14
Mon 15
Tue 16
Wed 17
Thu 18
Fri 19
Sat 20
Sun 21
Mon 22
Tue 23
Wed 24
Thu 25
Fri 26
Sat 27
Sun 28
Mon 29
Tue 30
Anadarko
690
F
PLAIN ST
756
214
% Seg Avail
72%
740
B
AMAR N
293
57
81%
AMAR S
310
75
76%
780
DUMAS E
170
100
41%
DUMAS S
311
32
90%
Lincoln Crossover
640
CAPROCK N
612
123
88
347
461
80%
86%
43%
25%
Line 1903
3060
CADEHR
511
100%
0%
North Mainline
200
NORTH ML
2251
124
235
296
645
94%
87%
71%
Permian Virtual Segment
940
KEYST ST
781
160
428
KEYSTAFL
750
128
396
L2000
608
80
PECOS
1195
105
WA2CORN
734
497
San Juan
110
BONDADST
726
166
82%
77%
South Mainline
1600
CORN HPW
589
354
CORN LPW
1182
133
309
233
CORNL2K
584
CORNTRN
151
2506
95%
88%
1640
EL PASO
1250
ELPASO C
593
ELPASO E
587
63
2430
97%
1680
AFTON
1051
405
HP 2
588
L2K-2
582
2221
1760
LORDS B
82
53
LORDS C
577
LORDSBRG
983
395
431
2144
78%
98%
1800
BOWIE
49
CIMARRON
575
DRAGOON
714
1871
96%
1885
WILCLAT
164
47%
1920
ORACLE
580
TOM MIX
572
VAIL
666
1818
2020
CASA C
570
CASAG LP
521
81
106
CG HP
578
1669
2160
WENDEN
2149
WENDWST
1528
873
3677
2500
EHRENBRG
2041
1384
32%
301016 (DSCALEHR)
1481
830
44%
301693 (INORBAJA)
952
441
54%
314980 (IBLYTHE)
0
Start Date
End Date
Region
Scheduling Location
Maintenance List
Base Capacity Dthd
Total Reduction Dthd
PLM Reduction Dthd
FMJ Reduction Dthd
Net Dthd
Update
09/03/25
SJ
Bondad 1B inspection
726,500
128,007
598,493
09/10/25
Line 1218 cleaning/smart tools Bondad to Blanco
166,732
559,768
09/01/25
09/08/25
NM
Flagstaff 2A equipment failure repair - FMJ Reduction
2,251,478
124,651
-
2,126,827
09/09/25
09/11/25
Flagstaff 2A equipment failure repair - FMJ Reduction Leupp 11A inspection Leupp D Station maintenance Window Rock 4A inspection
235,794
111,143
2,015,684
09/12/25
09/22/25
09/23/25
09/25/25
Flagstaff 2A equipment failure repair - FMJ Reduction Navajo 2C inspection
296,075
171,424
1,955,403
09/26/25
09/29/25
09/30/25
Flagstaff 2A equipment failure repair - FMJ Reduction Line 1200 cleaning tool Gallup to Window Rock Window Rock 2A inspection
645,151
520,500
1,606,327
XO
Laguna Station equipment failure repair - FMJ Reduction Line 1301 pipeline maintenance Bluewater to Valve City Roswell Station maintenance
612,700
123,246
45,941
77,305
489,454
09/15/25
Laguna Station equipment failure repair - FMJ Reduction Line 1301 pipeline maintenance Bluewater to Valve City
88,973
11,668
523,727
09/16/25
09/17/25
Laguna Station equipment failure repair - FMJ Reduction Line 1301 pipeline maintenance Bluewater to Valve City Bluewater Station DOT/ESD Tests
347,250
269,945
265,450
09/18/25
Laguna Station equipment failure repair - FMJ Reduction Line 1301 pipeline maintenance Bluewater to Valve City Bluewater Station DOT/ESD Tests - Reduced Outage Duration
09/19/25
Laguna Station equipment failure repair - FMJ Reduction Line 1301 pipeline maintenance Bluewater to Valve City Line 1300 cleaning tool Belen to Laguna
461,500
384,195
151,200
09/24/25
Laguna Station equipment failure repair - FMJ Reduction Line 1301 pipeline maintenance Bluewater to Valve City Line 1300 smart tools Belen to Laguna
AN
Dumas Station maintenance
170,500
100,150
70,350
311,400
32,370
279,030
Dimmitt 2A maintenance Amarillo 1A equipment failure repair - FMJ Reduction
293,300
57,941
235,359
310,400
75,041
PR
Plains 3A repair Plains 8A repair Plains 12A repair Plains 14A repair Plains 15A repair
756,100
214,860
541,240
Keystone 11A repair Keystone 12A repair Keystone 2B repair
781,000
160,198
620,802
Keystone 11A repair Keystone 12A repair Keystone 2B repair Keystone Station DOT/ESD Tests
428,357
352,643
09/20/25
750,400
128,137
622,263
396,323
354,077
09/05/25
Line 1600 cleaning tool Gresham to Cornudas Line 1600 smart tool Gresham to Cornudas
734,400
497,425
236,975
09/13/25
Pecos River Station DOT/ESD Tests
1,195,600
105,289
1,090,311
SM
Hueco 3A equipment failure repair - FMJ Reduction Hueco 1A maintenance Cornudas 1A equipment failure repair - FMJ Reduction
1,182,500
133,420
46,343
87,077
1,049,080
Hueco 3A equipment failure repair - FMJ Reduction Hueco 1A maintenance Cornudas 1A equipment failure repair - FMJ Reduction Cornudas A Station DOT/ESD Tests
309,792
222,715
872,708
Hueco 3A equipment failure repair - FMJ Reduction Hueco 1A maintenance Cornudas 1A equipment failure repair - FMJ Reduction Hueco Station DOT/ESD Tests
233,249
146,172
949,251
Line 1103 cleaning tool Afton to Deming
1,051,500
405,188
646,312
09/02/25
Line 1103 cleaning tool San Simon to Benson
983,500
395,646
587,854
09/04/25
Line 1103 smart tools San Simon to Benson
431,465
552,035
Line 2163 smart tool Willcox Lateral
309,468
164,468
145,000
Line 1103 cleaning tool Tucson to Casa Grande
521,600
81,340
440,260
Line 1103 smart tool Tucson to Casa Grande
106,415
415,185
MOJ
Line 2000 hydrotest Wenden to Ehrenberg Line 20118 pipeline maintenance Wenden to Ehrenberg Line 1903 capacity to South Mainline set to zero Dth/d during Line 2000 hydrotest Wenden to Ehrenberg and Line 20118 pipeline maintenance Wenden to Ehrenberg - Reference Critical Notice ID: 625908
511,000
Line 2000 hydrotest Wenden to Ehrenberg - Reference Critical Notice ID: 625908 Line 20118 pipeline maintenance Wenden to Ehrenberg - Reference Critical Notice ID: 625908
1,528,700
873,395
655,305
2,041,700
1,384,150
657,550
301693
North Baja Delivery - (INORBAJA) - Customer limited to CADIZSOU Line 1903 volume during Line 2000 hydrotest Wenden to Ehrenberg and Line 20118 pipeline maintenance Wenden to Ehrenberg - Reference Critical Notice ID: 625908
952,680
441,680
301016
So Cal Ehrenberg Delivery and Ehrenberg City Gate Delivery - (DSCALEHR) - Customer limited to 651,450 Dth/d during Line 2000 hydrotest Wenden to Ehrenberg and Line 20118 pipeline maintenance Wenden to Ehrenberg - Reference Critical Notice ID: 625908
1,481,910
830,460
651,450
314980
Blythe Power Plant Delivery - (IBLYTHE) - Customer currently not impacted during Line 2000 hydrotest Wenden to Ehrenberg and Line 20118 pipeline maintenance Wenden to Ehrenberg - Informational Only - Reference Critical Notice ID: 625908
80,000
El Paso 4D maintenance
608,300
80,421
527,879
584,600
57,133
527,467
587,400
63,998
523,402
589,800
354,753
235,047
Oracle Station inspection
584,400
82,365
502,035
Bowie Station maintenance
53,333
531,067
582,400
82,408
499,992
49,534
532,866
580,300
80,308
In addition to planned outages, this report reflects the repairs and maintenance being performed related to Force Majeure events.
Due to the nature of such events, the dates for the associated repairs and maintenance of those events are assumed to extend until the end of the month.
These repairs and maintenance, however, may extend beyond the end of the month including beyond the current year.
More information on these repairs and maintenance will be posted as a Critical Notice under the Notices section of the Informational Postings tab on the EPNG Electronic Bulletin Board.