EPNG Maintenance Calendar
November 2024
Location
Base Capacity (MDth)
Fri 1
Sat 2
Sun 3
Mon 4
Tue 5
Wed 6
Thu 7
Fri 8
Sat 9
Sun 10
Mon 11
Tue 12
Wed 13
Thu 14
Fri 15
Sat 16
Sun 17
Mon 18
Tue 19
Wed 20
Thu 21
Fri 22
Sat 23
Sun 24
Mon 25
Tue 26
Wed 27
Thu 28
Fri 29
Sat 30
AMAR N
313
18
98
AMAR S
312
9
97
BONDADST
742
150
79
39
CAPROCK N
621
247
113
240
CASA C
589
53
0
CORN LPW
1203
51
DRAGOON
720
103
DUMAS E
171
100
DUMAS S
32
DUTCH F
645
255
55
ELPASO C
617
54
FLOR B
620
FLORIDA
1008
58
GILA
649
181
GUADLUP
1197
106
211
KEYST ST
703
LORDSBRG
1017
114
559
156
MOJAVE
400
MOJTHRU
463
117
NORTH ML
2299
750
516
656
360
319
144
217
PECOS
1263
166
273
PLAIN ST
756
214
SJ TRI
2886
TOM MIX
591
22
IEDWRDPL (47817)
160
ITEXNEUN (377034)
77
Start Date
End Date
Region
Scheduling Location
Maintenance List
Base Capacity Dthd
Reduction Dthd
Net Dthd
Update
11/05/24
SJ
Bondad 1A inspection Line 1218 cleaning/smart tools Bondad to MLV 1
741,900
150,004
591,896
11/06/24
Bondad 1B inspection Line 1218 cleaning/smart tools Bondad to MLV 1
11/07/24
Line 1218 cleaning/smart tools Bondad to MLV 1
79,133
662,767
11/19/24
Line 1218 cleaning/smart tools Bondad to Blanco
38,900
703,000
11/13/24
11/14/24
Line 1212 cleaning/smart tools MLV 1 to MLV 3.25 - Rescheduled Line 1212 smart tool MLV 1 to MLV 3.25 - Rescheduled
2,885,800
-
11/20/24
11/22/24
Line 1212 cleaning/smart tools MLV 1 to MLV 3.25 - Informational Only - No Current Capacity Impact at SJ TRI
11/01/24
11/03/24
NM
Flagstaff 2A repair - FMJ Reduction -123,896 Dth/d Line 1200 pipeline remediation Seligman to Hackberry Line 1201 Hydrotest Seligman to Hackberry Line 1204 Hydrotest Window Rock to Navajo Window Rock 4B maintenance
2,299,037
749,509
1,549,528
11/04/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1200 pipeline remediation Seligman to Hackberry Line 1201 Hydrotest Seligman to Hackberry Line 1204 Hydrotest Window Rock to Navajo Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Rescheduled Window Rock 4B maintenance
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1200 pipeline remediation Seligman to Hackberry Line 1201 Hydrotest Seligman to Hackberry Line 1204 Hydrotest Window Rock to Navajo Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Rescheduled Window Rock 4B maintenance Window Rock 6B inspection
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1200 pipeline remediation Seligman to Hackberry Line 1201 Hydrotest Seligman to Hackberry Line 1204 Hydrotest Window Rock to Navajo - Completed Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Rescheduled Window Rock 4B maintenance Window Rock 6B inspection
516,015
1,783,022
11/08/24
11/09/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1200 pipeline remediation Seligman to Hackberry Line 1201 Hydrotest Seligman to Hackberry Line 1204 Hydrotest Window Rock to Navajo - Completed Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Rescheduled Window Rock 4B maintenance
11/10/24
11/11/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1200 pipeline remediation Seligman to Hackberry Line 1201 Hydrotest Seligman to Hackberry Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Rescheduled Window Rock 4B maintenance
11/12/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Rescheduled Window Rock 4B maintenance Window Rock 5B inspection Hackberry Station maintenance Leupp 5A maintenance
656,116
1,642,921
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Postponed Line 1200 pipeline repair Dilkon to Flagstaff Window Rock 4B maintenance Window Rock 5B inspection Leupp 6A maintenance - Completed
359,520
1,939,517
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Postponed Line 1200 pipeline repair Dilkon to Flagstaff Window Rock 4B maintenance Window Rock 5B inspection
11/15/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Postponed Line 1200 pipeline repair Dilkon to Flagstaff Window Rock 4B maintenance
11/16/24
11/18/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry - Completed Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Revised Project Schedule - Postponed Line 1200 pipeline repair Dilkon to Flagstaff Window Rock 4B maintenance
318,635
1,980,402
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry - Completed Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Postponed Line 1200 pipeline repair Dilkon to Flagstaff - Completed Window Rock 4B maintenance
144,048
2,154,989
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry - Completed Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Postponed Line 1200 pipeline repair Dilkon to Flagstaff - Completed Navajo 2C inspection Window Rock 4B maintenance
216,648
2,082,389
11/21/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry - Completed Line 1204 pipeline maintenance MLV 33.25 to MLV 33.625 - Postponed Window Rock 4B maintenance
11/23/24
11/30/24
Flagstaff 2A repair - FMJ Reduction - 123,896 Dth/d Line 1201 Hydrotest Seligman to Hackberry - Completed Window Rock 4B maintenance
HX
Wenden Station maintenance
644,900
254,686
390,214
Wenden B Station maintenance - Rescheduled
Wenden B Station maintenance
54,651
590,249
XO
Roswell Station repair - FMJ Reduction - 113,420 Dth/d Caprock Station repair - FMJ Reduction - 179,386 Dth/d
621,000
246,565
374,435
Roswell Station repair - FMJ Reduction - 113,420 Dth/d Capock Station repair - Completed
113,420
507,580
Bluewater Station maintenance Roswell Station repair - FMJ Reduction - 113,420 Dth/d Capock Station repair - Completed
239,771
381,229
AN
Dimmitt 3A maintenance
312,700
17,899
294,801
Dimmitt 3A maintenance Amarillo 1A maintenance
97,700
215,000
312,000
9,277
302,723
97,000
Dumas Station maintenance - Rescheduled
313,000
Dumas Station maintenance
32,000
281,000
170,900
100,200
70,700
PR
Plains 3A repair Plains 8A repair Plains 13A repair Plains 15A repair
756,100
213,838
542,262
377034
Eunice 3C mechanical Inspection no flow at ITEXNEUN (377034) during this maintenance only. Alternate scheduling location IWAREUNI - Rescheduled
76,545
Keystone 9A repair
703,052
50,702
652,350
47817
47817 - Edwards Plant Receipt - Customer to zero Dth/d for 8 hours during planned meter station maintenance with the customer - Rescheduled
160,000
47817 - Edwards Plant Receipt - Customer to zero Dth/d for 8 hours during planned meter station maintenance with the customer
53,000
107,000
Line 1100 pipeline repair Pecos River to Guadalupe - FMJ Reduction - 166,131 Dth/d
1,262,600
166,131
1,096,469
Line 1100 pipeline repair Pecos River to Guadalupe - FMJ Reduction - 166,131 Dth/d Line 1103 pipeline replacement Pecos River to Guadalupe - Rescheduled
Line 1100 pipeline repair Pecos River to Guadalupe - Completed Line 1103 pipeline replacement Pecos River to Guadalupe - Rescheduled
Line 1103 pipeline replacement Pecos River to Guadalupe
272,943
989,657
11/17/24
Line 1103 pipeline replacement Pecos River to Guadalupe - Extended
Line 1100 pipeline repair Pecos River to Guadalupe - FMJ Reduction - 105,536 Dth/d
1,196,800
105,536
1,091,264
Line 1100 pipeline repair Pecos River to Guadalupe - FMJ Reduction - 105,536 Dth/d Line 1103 pipeline replacement Pecos River to Guadalupe - Rescheduled
Line 1100 pipeline repair Pecos River to Guadalupe - FMJ Reduction - 105,536 Dth/d - Completed Line 1103 pipeline replacement Pecos River to Guadalupe - Rescheduled
211,366
985,434
SM
Cornudas 2A maintenance
1,202,600
50,770
1,151,830
Florida 3A maintenance
1,008,000
58,183
949,817
Lordsburg 1A maintenance
1,016,600
114,300
902,300
Line 1103 cleaning/smart tools Deming to San Simon - Cancelled Lordsburg 1A maintenance
Line 1103 cleaning/smart tools Deming to San Simon - Rescheduled Lordsburg 1A maintenance
Lordsburg 1A maintenance Line 1103 cleaning/smart tools Deming to San Simon
558,659
457,941
Lordsburg 1A maintenance - Extended
Lordsburg 1A maintenance - Extended San Simon 3A inspection
155,922
860,678
Line 1100 pipeline maintenance Dragoon to Vail
719,900
103,444
616,456
Line 1100 pipeline maintenance Dragoon to Vail - Informational Only (Revised Capacity Impact)
PHX
Line 1100 hydrotest Casa Grande to Gila Line 1100 pipeline maintenance MLV 77 and MLV 79
648,600
180,913
467,687
Tom Mix 1A inspection
591,400
22,422
568,978
Tom Mix 1A inspection - Revised Outage Schedule
Casa Grande 1C repair - FMJ Reduction - 52,626 Dth/d
588,900
52,626
536,274
Casa Grande C Station maintenance - Rescheduled Casa Grande 1C repair - FMJ Reduction - 52,626 Dth/d
Casa Grande 1C repair - Completed
Update Cycle 3
El Paso 1C maintenance
617,100
54,334
562,766
El Paso 1C maintenance - Completed
Line 1600 Leak Repair Florida B to Lordsburg B - FMJ Reduction - 620,100 Dth/d
620,100
Line 1600 Leak Repair Florida B to Lordsburg B - Completed
MOJ
Mojave 3A inspection
400,000
54,000
346,000
463,000
117,000