Wyoming Interstate Company
Operations Planning Report February 2026
Reissued February 5, 2026
Pipe
Start Date
End Date
County, ST
Scheduling Location
Maintenance List
Base Capacity (Dth)
Reduction (Dth)
Net (Dth)
Flow Indication
Update
WIC
2/11/26
CARBON, WY
428_WIC ECHO SPRINGS LATERAL
Creston Station maintenance
132,000
0
TD1
50,000
Cycle 4 82,000
2/1/26
2/4/26
CONVERSE, WY
440_WIC DOUGLAS COMPRESSOR STATION
Notice of Force Majeure - Segment 440 Reference Notice # 122861 Douglas Unit # 1 and 3
750,000
375,000
2/5/26
2/28/26
Revision Unit #1 Repair Completed Force Majeure Update Reference Notice # 122879 Notice of Force Majeure - Segment 440 Reference Notice # 122861 Douglas Unit # 1 and 3
1,075,000
325,000
Cycle 3 Update
In addition to planned outages, this report reflects the repairs and maintenance being performed related to Force Majeure events.
Due to the nature of such events, the dates for the associated repairs and maintenance of those events are assumed to extend until the end of the month.
These repairs and maintenance, however, may extend beyond the end of the month, including beyond the current year.
More information on these repairs and maintenance will be posted as a Critical Notice under the Notices section of the Informational Postings tab on the WIC Electronic Bulletin Board