Wyoming Interstate Company
Operations Planning Report September 2025
Reissued September 8, 2025
Pipe
Start Date
End Date
County, ST
Scheduling Location
Maintenance List
Base Capacity (Dth)
Reduction (Dth)
Net (Dth)
Flow Indication
Update
WIC
6/17/25
9/19/25
SWEETWATER, WY
420_THREEMILE LATERAL TO REX
Revision WIC extends the End Date from 9/10 to 9/19 Wamsutter Jumper Station Maintenance
295,000
0
TD1
9/8/25
9/12/25
CARBON, WY
428_WIC ECHO SPRINGS LATERAL
Creston Station DOT/ESD Test and maintenance
132,000
50,000
Cycle 4 82,000
ALBANY,WY
438_EAST OF POWDER RIVER - CO
Line 124A 36" pipeline hydro test MLV 4 to Laramie Station
550,000
438_EAST OF POWDER RIVER - CO_BH
220,000
TD2