Effective Intraday 2 Cycle (18:00) for the gas day of Friday, November 20, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 ON THE 500 lINE FROM STA 527 TO STA 542 FOR OVERTAKES from the system OR UNDERDELIVERieS into the SYSTEM FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES
DAILY IMBALANCE WARNING FOR ALL AREAS EAST OF STA 245 AND STA 321 FOR OVERTAKES FROM THE SYSTEM OR UNDERDELIVERIES INTO THE SYSTEM FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES
SEGMENT RESTRICTIONS
· STA 542 (Segment 539 BH) - through PIP increases due to force majeure
· STA 409 - Donna Lateral (Segment 490 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 15,850 Dths
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 11,029 Dths
· STA 523 West (Segment 516 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 57,852 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 454,735 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 298,218 Dths
· STA 315 (Segment 315 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 287,056 Dths
· STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 78,608 Dths
· STA 321 (Segment 321 FH) - through approx 52% of SOP increases due to nominations in excess of operational capacity; 58,419 Dths
· MLV 330 (Segment 324 FH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 25,503 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 259,052 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 269,749 Dths
· STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 190,296 Dths
· MLV 273 (Segment 284 FH) - through approx 51% of SOP increases due to nominations in excess of operational capacity; 44,321 Dths
LINEPACK RESTRICTIONS
PAYBACK NOMINATIONS WILL BE EVALUATED AT EACH CYCLE AND SCHEDULED ONLY IF OPERATIONALLY FEASIBLE.
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD or PAL-AO services
Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed with partner approvals.
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.