Effective Timely Cycle (9:00) for the gas day of Sunday, September 20, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 ON THE 500 lINE FROM STA 527 TO STA 542 FOR OVERTAKES from the system OR UNDERDELIVERieS into the system FOR ALL LMPA, SA ACTING AS BALANCING PARTIES AND LMMA BALANCING PARTIES
ofo daily critical day 1 for all areas east of sta 219 for overdeliveries into the system or undertakes out of the system for all lmpa, sa acting as balancing parties and lmma balancing parties
METER RESTRICTIONS
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPss due to operational concerns; 5,000 Dths
· TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of IT due to operational concerns; 17 Dths
· FGT/TGP Carnes Mississippi Stone Delivery Meter (Pin 420366) - through 100% of PIP due to planned and unplanned maintenance
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 20,000 Dths
· Greenbrier Tn 2 (Dual) Receipt Meter (Pin 420289) - through 100% of SOP receipts due to displacement gas unavailable for backhaul; 13,801 Dths
· GULFSTH/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through 100% of SIPps due to operational concerns; 7,600 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10,000 Dths
· UGIAPP/TGP Brinker No.2 Columbiana Receipt Meter (Pin 47882) - through approx 13% of SA due to nominations in excess of operational capacity; 9,498 Dths
· UGIAPP/TGP Farmer Brothers Columbia Receipt Meter (Pin 53950) - through approx 48% of IT due to nominations in excess of operational capacity; 79,633 Dths
· BLCKHILL/TGP Swain Road Dehy: Rip 3 Receipt Meter (Pin 412785) - through approx 54% of SA due to nominations in excess of operational capacity; 37,314 Dths
· NRGBM/TGP Beirne Hill Sales Bradfor Delivery Meter (Pin 48061) - through approx 2% of IT due to nominations in excess of operational capacity; 2,404 Dths
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP due to operational concerns; 57,632 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP due to nominations in excess of operational capacity; 4,494 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 22,263 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 29,864 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 88% of SOP due to nominations in excess of operational capacity; 360,727 Dths
· STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 427,555 Dths
· STA 317 (Segment 317 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 170,172 Dths
· STA 321 (Segment 321 FH) - through approx 38% of SOP due to nominations in excess of operational capacity; 408,182 Dths
· STA 325 (Segment 324 FH) - through approx 12% of SOP due to nominations in excess of operational capacity; 60,716 Dths
· MLV 330 (Segment 324 FH) - through approx 30% of SOP due to nominations in excess of operational capacity; 178,128 Dths
· Z5hc North (Segment 299 FH) - through approx 76% of SOP due to nominations in excess of operational capacity; 567,600 Dths
· STA 245 (Segment 245 FH) - through approx 81% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 691,227 Dths
· STA 249 (Segment 249 FH) - through approx 59% of SOP due to nominations in excess of operational capacity; 330,775 Dths
· STA 254 (Segment 249 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 136,228 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 76% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 133,019 Dths
· MLV 273 (Segment 284 FH) - through approx 98% of SOP due to nominations in excess of operational capacity; 262,766 Dths
LINEPACK RESTRICTIONS
PAYBACK NOMINATIONS WILL BE EVALUATED AT EACH CYCLE AND SCHEDULED ONLY IF OPERATIONALLY FEASIBLE.
STORAGE RESTRICTIONS
No Authorized Overrun Injections Services under Rate Schedule FS-AO at the following storage fields:
o Northern MA (460018) storage field
o Portland MA (460025) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service in Zones 4, 5 and 6
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service in Zones 4, 5 and 6
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.