Effective Timely Cycle (9:00) for the gas day of Monday, June 15, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· NMP/TGP Gillrina Road Nueces Delivery Meter (Pin 47799) - through approx 25% of SIPps due to nominations in excess of operational capacity; 74,195 Dths
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 20,000 Dths
· LEAF/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP due to pipeline maintenance at delivery location; 1,104 Dths
· Div PROD/TGP Mason Dehy: Rip 315F 1 Receipt Meter (Pin 412858) - through 100% of SOP deliveries due to displacement gas unavailable for backhaul; 89,752 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 37% of SIPps due to nominations in excess of operational capacity; 151,333 Dths
SEGMENT RESTRICTIONS
· STA 534 South Of Pool (Segment 530 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 6,271 Dths
· STA 1 (Segment 101 BH) - through approx 48% of SOP due to operational concerns; 42,748 Dths
· MLV 509 Muskrat Line (Segment 515 BH) - through 100% of SOP due to nominations in excess of operational capacity; 2,500 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 10,000 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 15,000 Dths
· STA 204 (Segment 204 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 358,652 Dths
· MLV 314 East (Segment 314 BH) - through approx 85% of SOP due to nominations in excess of operational capacity; 422,942 Dths
· STA 315 (Segment 315 BH) - through approx 82% of SOP due to nominations in excess of operational capacity; 529,464 Dths
· STA 317 (Segment 317 BH) - through approx 37% of SOP due to nominations in excess of operational capacity; 42,231 Dths
· STA 321 (Segment 321 FH) - through approx 42% of SOP due to nominations in excess of operational capacity; 424,539 Dths
· MLV 330 (Segment 324 FH) - through approx 37% of SOP due to nominations in excess of operational capacity; 223,270 Dths
· Z5hc North (Segment 299 FH) - through approx 83% of SOP due to nominations in excess of operational capacity; 633,332 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 881,097 Dths
· STA 249 (Segment 249 FH) - through approx 65% of SOP due to nominations in excess of operational capacity; 332,494 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 13% of SOP due to nominations in excess of operational capacity; 22,024 Dths
· MLV 273 (Segment 284 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 218,521 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Your session will expire in . Click OK to renew your session.