Project Updates
"***Sta 563 Joelton: Unit 2A - Solar Turbine Exchange
--6/8/26 through 6/19/26: This project will require a unit outage, which will limit throughput through the station and result in restrictions based on customer nominations.
***
Date Change, Previously scheduled 5/11/26 to 5/22/26.
………………………………"
"***Sta 860: Annual ESD Test & Maintenance
--6/1/26 through 6/5/26: This project will require a station outage, which will limit throughput through the station and result in restrictions based on customer nominations.
Date Change, Previously scheduled 6/8/26 to 6/12/26.
"***Sta 860: Scrubber/Filter/Separator Clean, Inspect & Filter Change
If you have any questions, please contact your Scheduler.