Effective Intraday 1 Cycle (14:00) for the gas day of Wednesday, May 06, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
ofo daily critical day 1 for over-deliveries into the system or under-takes out of the system for various parts of the system (see notice identifier 401108) for lmmas, lmpas and sas acting as balancing parties only
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 13,193 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 842 Dths
· STA 523 West (Segment 516 FH) - through approx 55% of SOP increases due to nominations in excess of operational capacity; 4,251 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 314,958 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 226,636 Dths
· STA 315 (Segment 315 BH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 339,855 Dths
· STA 317 (Segment 317 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 56,083 Dths
· STA 321 (Segment 321 FH) - through approx 55% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 141,863 Dths
· MLV 330 (Segment 324 FH) - through approx 52% of SOP increases due to nominations in excess of operational capacity; 28,566 Dths
· MLV 355 (Segment 355 BH) - through 100% of SOP increases due to operational concerns; 6,024 Dths
· Z5hc North (Segment 299 FH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 163,116 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 254,236 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 18,140 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Your session will expire in . Click OK to renew your session.