Effective Timely Cycle (9:00) for the gas day of Friday, March 27, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of IT due to operational concerns; 20,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 5,000 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through approx 50% of SOP due to nominations in excess of operational capacity; 30,790 Dths
· STA 823 (Segment 823 BH) - through approx 7% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 4,856 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 4,200 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 421,132 Dths
· MLV 314 East (Segment 314 BH) - through approx 96% of SOP due to nominations in excess of operational capacity; 546,113 Dths
· STA 315 (Segment 315 BH) - through approx 83% of SOP due to nominations in excess of operational capacity; 586,059 Dths
· STA 317 (Segment 317 BH) - through approx 48% of SOP due to nominations in excess of operational capacity; 64,840 Dths
· STA 321 (Segment 321 FH) - through approx 54% of SOP due to nominations in excess of operational capacity; 610,829 Dths
· STA 325 (Segment 324 FH) - through approx 22% of SOP due to nominations in excess of operational capacity; 113,804 Dths
· MLV 330 (Segment 324 FH) - through approx 47% of SOP due to nominations in excess of operational capacity; 257,838 Dths
· MLV 336 East (Segment 336 FH) - through approx 96% of SOP due to nominations in excess of operational capacity; 85,316 Dths
· STA 224 (Segment 224 FH) - through approx 35% of SOP due to nominations in excess of operational capacity; 53,219 Dths
· Z5hc North (Segment 299 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 690,690 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 981,548 Dths
· STA 249 (Segment 249 FH) - through approx 95% of SOP due to nominations in excess of operational capacity; 597,527 Dths
· MLV 273 (Segment 284 FH) - through approx 92% of SOP due to nominations in excess of operational capacity; 281,067 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
· No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:
o Northern MA (460018)
o Portland MA (460025)
o Portland PA (460020)
o Bear Creek PA (460017)
· Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) until further notice
· No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:
o Pine Prairie Virtual (54628)
· No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:
o Northern MA (460018) IS-MA
o Bear Creek PA (460017) IS-PA
· No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.