Effective Evening Cycle (9:00) for the gas day of Tuesday, March 10, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
none
METER RESTRICTIONS
· TGP/SNG Pugh Mississippi Exch Lownd Receipt Meter (Pin 420294) - through 100% of SOP increases due to operational concerns; 2,500 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 36,015 Dths
· STA 823 (Segment 823 BH) - through approx 6% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,830 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 8,420 Dths
· STA 860 South 500 Line (Segment 548 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,200 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 367,132 Dths
· MLV 314 East (Segment 314 BH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 275,403 Dths
· STA 315 (Segment 315 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 566,164 Dths
· STA 317 (Segment 317 BH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 77,062 Dths
· STA 321 (Segment 321 FH) - through approx 30% of SOP increases due to nominations in excess of operational capacity; 61,140 Dths
· MLV 330 (Segment 324 FH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 41,586 Dths
· Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 250,880 Dths
· STA 245 (Segment 245 FH) - through approx 80% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 324,516 Dths
· STA 249 (Segment 249 FH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 260,173 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
· No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:
o Northern MA (460018)
o Portland MA (460025)
o Portland PA (460020)
o Bear Creek PA (460017)
· Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) until further notice
· No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:
o Pine Prairie Virtual (54628)
· No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:
o Northern MA (460018) IS-MA
o Bear Creek PA (460017) IS-PA
· No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.