Effective Intraday 2 Cycle (18:00) for the gas day of Tuesday, February 17, 2026 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Wright Receipt Meter (Pin 412181) - through approx 33% of SOP increases due to nominations in excess of operational capacity; 35,836 Dths
SEGMENT RESTRICTIONS
· Toca Lateral (Segment 529 FH) - through approx 96% of IT increases due to nominations in excess of operational capacity; 28,693 Dths
· STA 25 (Segment 125 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 29,268 Dths
· STA 47 (Segment 143 FH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 48,905 Dths
· STA 63 (Segment 163 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 16,657 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 7,775 Dths
· STA 307 (Segment 307 BH) - through approx 67% of SOP increases due to nominations in excess of operational capacity; 66,966 Dths
· MLV 314 East (Segment 314 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 105,449 Dths
· STA 317 (Segment 317 BH) - through approx 51% of SOP increases due to nominations in excess of operational capacity; 59,527 Dths
· STA 321 (Segment 321 FH) - through approx 32% of SOP increases due to nominations in excess of operational capacity; 37,397 Dths
· MLV 330 (Segment 324 FH) - through approx 86% of SOP increases due to nominations in excess of operational capacity; 113,815 Dths
· STA 219 North (Segment 219 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 11,063 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 125,200 Dths
· Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 269,436 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 394,538 Dths
· STA 254 (Segment 249 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 67,465 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 316 Dths
LINEPACK RESTRICTIONS
Payback nominations will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
· No Authorized Overrun Withdrawal Services under Rate Schedule FS-AO at the following storage fields:
o Northern MA (460018)
o Portland MA (460025)
o Portland PA (460020)
o Bear Creek PA (460017)
· Customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) until further notice
· No Authorized Overrun Withdrawal Services under Rate Schedule FS-F at the following storage field:
o Pine Prairie Virtual (54628)
· No Interruptible Storage Withdrawal Services under Rate Schedule IS at the following storage fields:
o Northern MA (460018) IS-MA
o Bear Creek PA (460017) IS-PA
· No Loans or Park Withdrawals under Rate Schedule PAL utilizing the PAL-D or PAL-AO services system-wide
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.