Project Updates
"***MLV 16-3 to MLV 17-3: Immediate Anomaly Dig
--12/1/25 through 12/12/25: This project may require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations.
***Added
***MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement
--11/1/25 through 12/13/25: This project will require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations. The meters listed will be shut in during the project. Potential secondary restrictions at the meter(s) may be at risk.
420212 DELTA NG/TGP SALT LICK KY BATH
420038 MOREHEAD/TGP MOREHEAD KY ROWAN
***
Date Change, Previously scheduled 11/1/25 to 11/26/25.
………………………………"
If you have any questions, please contact your Scheduler.