Effective Timely Cycle (9:00) for the gas day of Wednesday, September 10, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through approx 4% of SA due to nominations in excess of operational capacity; 9,932 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 20,000 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 8% of SIPps due to nominations in excess of operational capacity; 141,650 Dths
· HAMVIL/TGP Village Of Hamilton Ny M Delivery Meter (Pin 47592) - through approx 2% of IT due to nominations in excess of operational capacity; 33 Dths
SEGMENT RESTRICTIONS
· STA 9 (Segment 109 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 108,535 Dths
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 17,824 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 17,088 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 10,100 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 11,000 Dths
· STA 204 (Segment 204 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 219 South (Segment 217 BH) - through 100% of SOP due to operational concerns; 21,300 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 608,714 Dths
· MLV 314 East (Segment 314 BH) - through approx 90% of SOP due to nominations in excess of operational capacity; 599,263 Dths
· STA 315 (Segment 315 BH) - through approx 83% of SOP due to nominations in excess of operational capacity; 693,836 Dths
· STA 317 (Segment 317 BH) - through approx 64% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 131,993 Dths
· STA 321 (Segment 321 FH) - through approx 51% of SOP due to nominations in excess of operational capacity; 533,591 Dths
· MLV 330 (Segment 324 FH) - through approx 31% of SOP due to nominations in excess of operational capacity; 149,633 Dths
· Z5hc North (Segment 299 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 753,095 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 948,333 Dths
· STA 249 (Segment 249 FH) - through approx 58% of SOP due to nominations in excess of operational capacity; 324,437 Dths
· MLV 256 East (Segment 256 FH) - through approx 57% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 71,497 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 267,544 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Your session will expire in . Click OK to renew your session.