Effective Evening Cycle (9:00) for the gas day of Saturday, September 06, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· WHISTLEP/TGP Whistle Receipt Nueces Receipt Meter (Pin 54847) - through approx 91 % of SA increases due to nominations in excess of operational capacity; 22,225 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP increases due to operational concerns; 1,795 Dths
SEGMENT RESTRICTIONS
· STA 823 (Segment 823 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 20,752 Dths
· MLV 548 (Segment 542 BH) - through SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 219 South (Segment 217 BH) - through approx 100 % of SOP increases due to operational concerns; 21,260 Dths
· STA 307 (Segment 307 BH) - through approx 84 % of SOP increases due to nominations in excess of operational capacity; 310,884 Dths
· MLV 314 East (Segment 314 BH) - through approx 83 % of SOP increases due to nominations in excess of operational capacity; 281,817 Dths
· STA 315 (Segment 315 BH) - through approx 82 % of SOP increases due to nominations in excess of operational capacity; 516,063 Dths
· STA 317 (Segment 317 BH) - through approx 54 % of SOP increases due to nominations in excess of operational capacity; 64,903 Dths
· STA 321 (Segment 321 FH) - through approx 60 % of SOP increases due to nominations in excess of operational capacity; 154,763 Dths
· STA 224 (Segment 224 FH) - through approx 52 % of SOP increases due to nominations in excess of operational capacity; 13,850 Dths
· Z5hc North (Segment 299 FH) - through approx 99 % of SOP increases due to nominations in excess of operational capacity; 305,716 Dths
· STA 245 (Segment 245 FH) - through approx 94 % of SOP increases due to nominations in excess of operational capacity; 396,847 Dths
· STA 249 (Segment 249 FH) - through approx 90 % of SOP increases due to nominations in excess of operational capacity; 235,034 Dths
· MLV 256 East (Segment 256 FH) - through approx 74 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 77,180 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.