Effective Evening Cycle (9:00) for the gas day of Friday, September 05, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 97% of SOP increases due to operational concerns; 7,909 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 4,731 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 34,843 Dths
· STA 834 (Segment 834 BH) - through approx 86% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 2,796 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 47 Dths
· STA 523 West (Segment 516 FH) - through approx 6% of SOP increases due to nominations in excess of operational capacity; 952 Dths
· MLV 548 (Segment 542 BH) - through SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 219 South (Segment 217 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 20,763 Dths
· STA 307 (Segment 307 BH) - through approx 87% of SOP increases due to nominations in excess of operational capacity; 305,722 Dths
· MLV 314 East (Segment 314 BH) - through approx 82% of SOP increases due to nominations in excess of operational capacity; 256,254 Dths
· STA 315 (Segment 315 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 373,837 Dths
· STA 317 (Segment 317 BH) - through approx 53% of SOP increases due to nominations in excess of operational capacity; 70,098 Dths
· STA 321 (Segment 321 FH) - through approx 38% of SOP increases due to nominations in excess of operational capacity; 89,325 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 160,000 Dths
· Z5 HC North (Segment 299 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 288,370 Dths
· STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 380,443 Dths
· STA 249 (Segment 249 FH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 229,343 Dths
· MLV 256 East (Segment 256 FH) - through approx 63% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 69,227 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 179,524 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.