Effective Intraday 1 Cycle (14:00) for the gas day of Saturday, August 30, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR UNDER-TAKES FROM THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through approx 41% of SA receipt increases due to displacement gas unavailable for backhaul; 19,285 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of SIPss increases due to nominations in excess of operational capacity; 30,662 Dths
SEGMENT RESTRICTIONS
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 19,519 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 24,927 Dths
· STA 114 East (Segment 114 BH) - through PIP increases due to force majeure at STA 119 Unit 1A
· STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 303,073 Dths
· MLV 314 East (Segment 314 BH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 259,403 Dths
· STA 317 (Segment 317 BH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 278,781 Dths
· STA 321 (Segment 321 FH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 83,865 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 160,000 Dths
· Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 281,229 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 338,627 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 125,683 Dths
· MLV 263 (Segment 261 FH) - through SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 179,524 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Your session will expire in . Click OK to renew your session.