Effective Intraday 3 Cycle (22:00) for the gas day of Monday, August 25, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR THE 500 LINE ONLY (SEGMENTS 527,529,530,534,539,542,548,860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· COKINOS/TGP Rasmussen Farm Tx Whart Delivery Meter (Pin 420442) - through approx 3% of IT increases due to nominations in excess of operational capacity; 10 Dths
SEGMENT RESTRICTIONS
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 929 Dths
· STA 114 East (Segment 114 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 204 (Segment 204 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 317 (Segment 317 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,961 Dths
· MLV 263 (Segment 261 FH) - through SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.