Effective Timely Cycle (9:00) for the gas day of Thursday, August 14, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· TGP/PHP Sheridan Colorado Receipt Meter (Pin 54086) - through approx 21% of SA due to operational concerns; 1,256 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 80% of SOP due to operational concerns; 79,720 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 55% of SIPss due to nominations in excess of operational capacity; 40,473 Dths
SEGMENT RESTRICTIONS
· STA 47 (Segment 143 FH) - through approx 24% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 80,726 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 800 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 25,444 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 10,793 Dths
· STA 204 (Segment 204 BH) - into PIP due to scheduled maintenance and nominations in excess of operational capacity
· STA 219 South (Segment 217 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 20,040 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 408,714 Dths
· MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 651,929 Dths
· STA 315 (Segment 315 BH) - through approx 87% of SOP due to nominations in excess of operational capacity; 803,108 Dths
· STA 317 (Segment 317 BH) - through approx 52% of SOP due to nominations in excess of operational capacity; 82,837 Dths
· STA 321 (Segment 321 FH) - through approx 45% of SOP due to nominations in excess of operational capacity; 407,799 Dths
· STA 325 (Segment 324 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 214,963 Dths
· STA 224 (Segment 224 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 180,000 Dths
· Z5hc North (Segment 299 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 741,402 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 911,001 Dths
· STA 249 (Segment 249 FH) - through approx 67% of SOP due to nominations in excess of operational capacity; 387,779 Dths
· MLV 256 East (Segment 256 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 170,180 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 46% of SOP due to nominations in excess of operational capacity; 108,846 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 412,588 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.