Effective Timely Cycle (9:00) for the gas day of Tuesday, July 29, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR THE 500 LINE AND ALL AREAS EAST OF STA 254 ON THE 200 LINE AND ALL AREAS EAST OF STA 325 ON THE 300 LINE FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 5,000 Dths
SEGMENT RESTRICTIONS
· STA 542 (Segment 539 BH) - through 100% of SA due to emergent repair at STA 542; 24,928 Dths
· STA 25 (Segment 125 FH) - through 100% of SOP due to force majeure at STA 25; 8,989 Dths
· STA 823 (Segment 823 BH) - through approx 41% of SOP due to nominations in excess of operational capacity; 12,886 Dths
· STA 860 (Segment 860 BH) - through 100% of IT due to scheduled maintenance and nominations in excess of operational capacity; 5,247 Dths
· STA 523 West (Segment 516 FH) - through 100% of SOP due to nominations in excess of operational capacity; 31,490 Dths
· STA 110 South (Segment 187 BH) - into PIP due to force majeure at STA 110
· STA 204 (Segment 204 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 100 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 426,098 Dths
· MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 661,575 Dths
· STA 315 (Segment 315 BH) - through approx 81% of SOP due to nominations in excess of operational capacity; 603,808 Dths
· STA 317 (Segment 317 BH) - through approx 44% of SOP due to nominations in excess of operational capacity; 74,726 Dths
· STA 321 (Segment 321 FH) - through approx 56% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 563,722 Dths
· MLV 330 (Segment 324 FH) - through approx 32% of SOP due to nominations in excess of operational capacity; 152,737 Dths
· Z5hc North (Segment 299 FH) - through approx 87% of SOP due to nominations in excess of operational capacity; 789,910 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 868,918 Dths
· STA 249 (Segment 249 FH) - through approx 58% of SOP due to nominations in excess of operational capacity; 348,592 Dths
· MLV 256 East (Segment 256 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 173,059 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 74% of SOP due to nominations in excess of operational capacity; 173,809 Dths
· MLV 265 (Segment 265 FH) - through SIPsp due to scheduled maintenance and nominations in excess of operational capacity
· MLV 273 (Segment 284 FH) - through 100% of SOP due to nominations in excess of operational capacity; 108,243 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.