Effective Evening Cycle (9:00) for the gas day of Friday, July 11, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP increases due to operational concerns; 99,720 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 5,451 Dths
· STA 523 West (Segment 516 FH) - through approx 89 % of SOP increases due to nominations in excess of operational capacity; 49,055 Dths
· MLV 548 (Segment 542 BH) - through approx 100 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,981 Dths
· STA 860 South 500 Line (Segment 548 BH) - through PIP increases due to scheduled maintenance and nominations in excess of operational capacity
· STA 307 (Segment 307 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 436,053 Dths
· MLV 314 East (Segment 314 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 323,407 Dths
· STA 315 (Segment 315 BH) - through approx 76 % of SOP increases due to nominations in excess of operational capacity; 237,081 Dths
· STA 317 (Segment 317 BH) - through approx 80 % of SOP increases due to nominations in excess of operational capacity; 66,457 Dths
· STA 321 (Segment 321 FH) - through approx 57 % of SOP increases due to nominations in excess of operational capacity; 135,338 Dths
· MLV 330 (Segment 324 FH) - through approx 2 % of SOP increases due to nominations in excess of operational capacity; 1,000 Dths
· STA 224 (Segment 224 BH) - through approx 86 % of SOP increases due to nominations in excess of operational capacity; 62,626 Dths
· Z5hc North (Segment 299 FH) - through approx 87 % of SOP increases due to nominations in excess of operational capacity; 340,764 Dths
· STA 245 (Segment 245 FH) - through approx 96 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 437,886 Dths
· STA 249 (Segment 249 FH) - through approx 79 % of SOP increases due to nominations in excess of operational capacity; 209,716 Dths
· MLV 256 East (Segment 256 FH) - through approx 55 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 96,306 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 41 % of SOP increases due to nominations in excess of operational capacity; 19,080 Dths
· MLV 273 (Segment 284 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 324,732 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Your session will expire in . Click OK to renew your session.