Effective Intraday 2 Cycle (18:00) for the gas day of Thursday, July 10, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 4,487 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through PIP increases due to operational concerns
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 70% of SIPps increases due to nominations in excess of operational capacity; 13,004 Dths
SEGMENT RESTRICTIONS
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 4,182 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 3,281 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 9,955 Dths
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 315,967 Dths
· STA 315 (Segment 315 BH) - through approx 79% of SOP increases due to nominations in excess of operational capacity; 259,504 Dths
· STA 317 (Segment 317 BH) - through approx 87% of SOP increases due to nominations in excess of operational capacity; 70,164 Dths
· STA 224 (Segment 224 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 42,014 Dths
· Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 286,399 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 511,286 Dths
· STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 170,163 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 188,677 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.
Your session will expire in . Click OK to renew your session.