Effective Intraday 1 Cycle (14:00) for the gas day of Thursday, April 17, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 70,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 5,000 Dths
· ANR/TGP Shadyside St Mary Delivery Meter (Pin 412684) - through 100% of SOP increases due to operational concerns; 10,000 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 52,190 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 2,618 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 347,462 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 275,299 Dths
· STA 315 (Segment 315 BH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 250,471 Dths
· STA 321 (Segment 321 FH) - through approx 96% of SOP increases due to emergent repair at STA 321 Unit 5B; 393,492 Dths
· Z5hc North (Segment 299 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 470,463 Dths
· STA 245 (Segment 245 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 389,686 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 246,553 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 162,693 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.