Effective Timely Cycle (9:00) for the gas day of Wednesday, April 16, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 70,000 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP due to operational concerns; 5,000 Dths
· TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 62% of SIPss due to nominations in excess of operational capacity; 67,517 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through 100% of IT due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths
· STA 823 (Segment 823 BH) - through approx 45% of SOP due to nominations in excess of operational capacity; 17,032 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths
· STA 307 (Segment 307 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 334,841 Dths
· MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 489,067 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 493,327 Dths
· STA 321 (Segment 321 FH) - through approx 95% of SOP due to nominations in excess of operational capacity and due to an emergent repair at STA 321 UNIT 5B; 911,677 Dths
· STA 325 (Segment 324 FH) - through approx 6% of SOP due to nominations in excess of operational capacity; 17,704 Dths
· MLV 330 (Segment 324 FH) - through approx 48% of SOP due to nominations in excess of operational capacity; 168,166 Dths
· MLV 336 East (Segment 336 FH) - through approx 79% of SOP due to nominations in excess of operational capacity; 39,417 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 892,585 Dths
· STA 245 (Segment 245 FH) - through approx 97% of SOP due to nominations in excess of operational capacity; 948,302 Dths
· STA 249 (Segment 249 FH) - through approx 82% of SOP due to nominations in excess of operational capacity; 535,350 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 61% of SOP due to nominations in excess of operational capacity; 115,216 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP due to nominations in excess of operational capacity; 427,723 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.