Effective Intraday 1 Cycle (14:00) for the gas day of Thursday, April 10, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 60,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 8,000 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 92% of SIPss increases due to nominations in excess of operational capacity; 38,391 Dths
SEGMENT RESTRICTIONS
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 9,411 Dths
· STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 20,012 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 410,642 Dths
· MLV 314 East (Segment 314 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 254,495 Dths
· STA 315 (Segment 315 BH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 142,261 Dths
· STA 321 (Segment 321 FH) - through 100% of PIP increases due to emergent repair at STA 321 UNIT 5B; 410,933 Dths
· MLV 330 (Segment 324 FH) - through approx 65% of SOP increases due to nominations in excess of operational capacity; 91,298 Dths
· Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 329,221 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 478,395 Dths
· STA 249 (Segment 249 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 291,358 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 88,287 Dths
· MLV 273 (Segment 284 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 159,256 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.