Effective Evening Cycle (9:00) for the gas day of Monday, April 07, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP increases due to operational concerns; 9,149 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 93 % of SIPss increases due to nominations in excess of operational capacity; 96,240 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 25,000 Dths
· STA 823 (Segment 823 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 8,932 Dths
· STA 114 East (Segment 114 BH) - through approx 100 % of IT increases due to scheduled maintenance and nominations in excess of operational capacity; 7,000 Dths
· STA 307 (Segment 307 BH) - through approx 100 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 433,714 Dths
· MLV 314 East (Segment 314 BH) - through approx 99 % of SOP increases due to nominations in excess of operational capacity; 297,433 Dths
· STA 315 (Segment 315 BH) - through approx 94 % of SOP increases due to nominations in excess of operational capacity; 517,647 Dths
· STA 321 (Segment 321 FH) - through approx 100 % of SOP increases due to emergent repair at STA 321 UNIT 5B; 635,308 Dths
· Z5hc North (Segment 299 FH) - through approx 99 % of SOP increases due to nominations in excess of operational capacity; 314,995 Dths
· STA 245 (Segment 245 FH) - through approx 99 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 444,469 Dths
· STA 249 (Segment 249 FH) - through approx 86 % of SOP increases due to nominations in excess of operational capacity; 262,105 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 100 % of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 52,664 Dths
· MLV 273 (Segment 284 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 203,781 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.