Effective Intraday 1 Cycle (14:00) for the gas day of Friday, April 04, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· LASERGTH/TGP Riverside Wilson 1 Nu Receipt Meter (Pin 412124) - through approx 19 % of SA increases due to nominations in excess of operational capacity; 1,917 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP increases due to operational concerns; 11,149 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 96 % of SIPss increases due to nominations in excess of operational capacity; 66,798 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 6,896 Dths
· STA 860 (Segment 860 BH) - through approx 100 % of PIP increases due to force majeure at STA 860; 6,000 Dths
· STA 307 (Segment 307 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 433,714 Dths
· MLV 314 East (Segment 314 BH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 283,011 Dths
· STA 315 (Segment 315 BH) - through approx 95 % of SOP increases due to nominations in excess of operational capacity; 433,528 Dths
· STA 321 (Segment 321 FH) - through approx 30 % of SOP increases due to emergent repair at STA 321 UNIT 5B; 49,792 Dths
· MLV 330 (Segment 324 FH) - through approx 43 % of SOP increases due to nominations in excess of operational capacity; 40,909 Dths
· Z5hc North (Segment 299 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 320,230 Dths
· STA 245 (Segment 245 FH) - through approx 98 % of SOP increases due to nominations in excess of operational capacity; 395,793 Dths
· STA 249 (Segment 249 FH) - through approx 96 % of SOP increases due to nominations in excess of operational capacity; 221,785 Dths
· MLV 273 (Segment 284 FH) - through approx 100 % of SOP increases due to nominations in excess of operational capacity; 222,389 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.