Effective Timely Cycle (9:00) for the gas day of Friday, April 04, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· LASERGTH/TGP Riverside Wilson 1 Nu Receipt Meter (Pin 412124) - through approx 14 % of SA due to nominations in excess of operational capacity; 1,917 Dths
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through approx 100 % of SIPss due to imbalance management quantity exceeded; 44,954 Dths
· TRNSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through approx 100 % of SOP due to operational concerns; 14,980 Dths
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through approx 100 % of SOP due to operational concerns; 4,953 Dths
· GULFSTH/TGP Worthy Road South Ouach Delivery Meter (Pin 49780) - through approx 100 % of SIPps due to operational concerns; 18,821 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 100 % of SOP due to operational concerns; 11,153 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 75 % of SIPss due to nominations in excess of operational capacity; 123,561 Dths
SEGMENT RESTRICTIONS
· STA 823 Muskrat Line (Segment 509 BH) - through approx 36 % of SOP due to nominations in excess of operational capacity; 11,749 Dths
· MLV 548 (Segment 542 BH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 30,000 Dths
· STA 307 (Segment 307 BH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 433,714 Dths
· MLV 314 East (Segment 314 BH) - through approx 93 % of SOP due to nominations in excess of operational capacity; 492,046 Dths
· STA 315 (Segment 315 BH) - through approx 82 % of SOP due to nominations in excess of operational capacity; 496,308 Dths
· STA 321 (Segment 321 FH) - through approx 56 % of SOP due to emergent repair at STA 321 UNIT 5B; 546,309 Dths
· MLV 330 (Segment 324 FH) - through approx 27 % of SOP due to nominations in excess of operational capacity; 127,237 Dths
· MLV 336 East (Segment 336 FH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 86,982 Dths
· MLV 355 (Segment 355Fh) - through approx 100 % of SOP due to operational concerns; 1,763 Dths
· Z5hc North (Segment 299 FH) - through approx 86 % of SOP due to nominations in excess of operational capacity; 771,238 Dths
· STA 245 (Segment 245 FH) - through approx 85 % of SOP due to nominations in excess of operational capacity; 831,124 Dths
· STA 249 (Segment 249 FH) - through approx 64 % of SOP due to nominations in excess of operational capacity; 434,681 Dths
· MLV 273 (Segment 284 FH) - through approx 93 % of SOP due to nominations in excess of operational capacity; 345,835 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.