Effective Timely Cycle (9:00) for the gas day of Tuesday, March 25, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· GDR/TGP Rio Bravo Hidalgo Delivery Meter (Pin 421017) - through approx 74% of PIP deliveries due to location off rate; 191,008 Dths
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss due to imbalance management quantity exceeded; 80,000 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SIPps due to operational concerns; 15,000 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 82% of SIPss due to nominations in excess of operational capacity; 94,086 Dths
SEGMENT RESTRICTIONS
· MLV 406 (Segment 406 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 39,241 Dths
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP due to emergent repair at STA 40; 29,943 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 50,000 Dths
· STA 860 South 500 Line (Segment 548 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 4,321 Dths
· STA 307 (Segment 307 BH) - through approx 79% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 210,053 Dths
· MLV 314 East (Segment 314 BH) - through approx 93% of SOP due to nominations in excess of operational capacity; 271,970 Dths
· STA 315 (Segment 315 BH) - through approx 77% of SOP due to nominations in excess of operational capacity; 381,807 Dths
· STA 321 (Segment 321 FH) - through approx 61% of due to emergent repair at STA 321 UNIT 5B; 505,646 Dths
· STA 325 (Segment 324 FH) - through approx 24% of SOP due to nominations in excess of operational capacity; 77,548 Dths
· MLV 330 (Segment 324 FH) - through approx 33% of SOP due to nominations in excess of operational capacity; 106,798 Dths
· MLV 336 East (Segment 336 FH) - through approx 98% of SOP due to nominations in excess of operational capacity; 121,046 Dths
· STA 224 (Segment 224 FH) - through approx 41% of IT due to nominations in excess of operational capacity; 71,128 Dths
· Z5hc North (Segment 299 FH) - through approx 88% of SOP due to nominations in excess of operational capacity; 641,679 Dths
· STA 245 (Segment 245 FH) - through approx 86% of SOP due to nominations in excess of operational capacity; 715,125 Dths
· STA 249 (Segment 249 FH) - through approx 69% of SOP due to nominations in excess of operational capacity; 327,079 Dths
· MLV 273 (Segment 284 FH) - through approx 77% of SOP due to nominations in excess of operational capacity; 155,229 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.