Effective Intraday 2 Cycle (18:00) for the gas day of Wednesday, March 19, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY (SEGMENTS 527, 529, 530, 534, 539, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· GDR/TGP Rio Bravo Hidalgo Delivery Meter (Pin 421017) - through 100% of PIP increases deliveries due to location off rate; 53,802 Dths
· Tres Palacios /TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPss increases due to imbalance management quantity exceeded; 80,000 Dths
· TRANSCO/TGP Kinder La Exch (Bi 1 Delivery Meter (Pin 420373) - through 100% of SOP increases due to operational concerns; 4,889 Dths
· TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
SEGMENT RESTRICTIONS
· STA 40 South Of Carthage (Segment 132 FH) - through 100% of SOP increases due to emergent repair at STA 40; 10,522 Dths
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to force majeure at STA 860; 1,324 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to emergent repair between STA 96-1 to MLV 101-1; 9,983 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 252,887 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 346,048 Dths
· STA 224 (Segment 224 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 50,834 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 222,574 Dths
· STA 245 (Segment 245 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 273,170 Dths
· MLV 273 (Segment 284 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 113,331 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.