Effective Timely Cycle (9:00) for the gas day of Thursday, March 06, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY (SEGMENTS 527, 529, 530, 534, 539, 542, 548, 860) FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through approx 100 % of SIPss due to imbalance management quantity exceeded; 148,859 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 13 % of SOP due to operational concerns; 9,094 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 93 % of SIPss due to nominations in excess of operational capacity; 156,769 Dths
· IROQUOIS/TGP Shelton Interconnect F Receipt Meter (Pin 412180) - through approx 58 % of IT (through a rate of .1459) due to nominations in excess of operational capacity; 34,502 Dths
· Wright Receipt Meter (Pin 412181) - through approx 7 % of IT (through a rate of .1980) due to nominations in excess of operational capacity; 19,762 Dths
SEGMENT RESTRICTIONS
· STA 40 South Of Carthage (Segment 132 FH) - through approx 100 % of SOP due to emergent repair at STA 40; 15,381 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 6,443 Dths
· STA 860 (Segment 860 BH) - through approx 100 % of SOP due to force majeure at STA 860; 7,212 Dths
· MLV 548 (Segment 542 BH) - through approx 100 % of SA due to scheduled maintenance and nominations in excess of operational capacity; 12,000 Dths
· STA 307 (Segment 307 BH) - through approx 33 % of SOP due to nominations in excess of operational capacity; 88,008 Dths
· MLV 314 East (Segment 314 BH) - through approx 74 % of SOP due to nominations in excess of operational capacity; 212,998 Dths
· STA 315 (Segment 315 BH) - through approx 56 % of SOP due to nominations in excess of operational capacity; 223,687 Dths
· STA 321 (Segment 321 FH) - through approx 76 % of SOP due to emergent repair at STA 321 UNIT 5B; 749,425 Dths
· STA 325 (Segment 324 FH) - through approx 29 % of SOP due to nominations in excess of operational capacity; 99,982 Dths
· MLV 330 (Segment 324 FH) - through approx 39 % of SOP due to nominations in excess of operational capacity; 171,802 Dths
· MLV 336 East (Segment 336 FH) - through approx 83 % of SOP due to nominations in excess of operational capacity; 93,542 Dths
· STA 224 (Segment 224 FH) - through approx 82 % of SOP due to nominations in excess of operational capacity; 198,472 Dths
· Z5hc North (Segment 299 FH) - through approx 89 % of SOP due to nominations in excess of operational capacity; 597,829 Dths
· STA 237 East Of Z5w Pool (Segment 237 FH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 333,944 Dths
· STA 245 (Segment 245 FH) - through approx 89 % of SOP due to nominations in excess of operational capacity; 422,352 Dths
· STA 249 (Segment 249 FH) - through approx 82 % of SOP due to nominations in excess of operational capacity; 385,565 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 32 % of SOP due to nominations in excess of operational capacity; 66,361 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Nominations for Authorized Overrun Withdrawal Services (FS-AO) at the Northern MA (460018) storage field, the Portland MA (460025) storage field, the Portland PA (460020) storage field or the Bear Creek PA (460017) storage field will not be allowed until further notice. Additionally, customers who elected swing on storage or storage swing options for balancing (SOS or SSO) may only swing up to their Maximum Daily Withdrawal (MDWQ) only until further notice.
Nominations for Firm Storage Flex Authorized Overrun (FSF-AO) Withdrawal Services under Rate Schedule FS-F at the Pine Prairie Virtual Meter (54628) will not be allowed until further notice.
Nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and nominations for Interruptible Storage Withdrawal Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field will not be allowed until further notice.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017)(IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals. Additionally, no transfers from IS-MA and IS-PA to FS will be allowed until further notice.
No Loans or Park Withdrawals under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide until further notice.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.