Effective Timely Cycle (9:00) for the gas day of Saturday, December 28, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 245 AND STA 336 FOR OVER-TAKES OUT OF THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Atmos KY/TGP Harrodsburg Ky Boyle Delivery Meter (Pin 420028) - through approx 6 % of IT due to nominations in excess of operational capacity; 302 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through approx 55 % of IT due to nominations in excess of operational capacity; 59,048 Dths
· STA 87 South 800 Line (Segment 860 BH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 28,814 Dths
· STA 110 South (Segment 187 BH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through approx 100 % of SOP due to scheduled maintenance and nominations in excess of operational capacity; 257,895 Dths
· MLV 314 East (Segment 314 BH) - through approx 69 % of SOP due to nominations in excess of operational capacity; 192,691 Dths
· STA 315 (Segment 315 BH) - through approx 67 % of SOP due to nominations in excess of operational capacity; 344,672 Dths
· STA 321 (Segment 321 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 790,154 Dths
· STA 325 (Segment 324 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 25,000 Dths
· MLV 336 East (Segment 336 FH) - through approx 44 % of SOP due to nominations in excess of operational capacity; 38,229 Dths
· STA 224 (Segment 224 FH) - through approx 51 % of SOP due to nominations in excess of operational capacity; 126,155 Dths
· Z5hc North (Segment 299 FH) - through approx 88 % of SOP due to nominations in excess of operational capacity; 574,553 Dths
· STA 245 (Segment 245 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 712,295 Dths
· STA 249 (Segment 249 FH) - through approx 65 % of SOP due to nominations in excess of operational capacity; 240,703 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 232,672 Dths
· MLV 273 (Segment 284 FH) - through approx 100 % of SOP due to nominations in excess of operational capacity; 42,889 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.