Effective Intraday 2 Cycle (18:00) for the gas day of Monday, December 23, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS EAST OF STA 219 ON THE 200 LINE AND ALL AREAS EAST OF STA 219 ON THE 300 LINE AND ALL OF THE HC LINE FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TRANSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Col GAS/TGP Milford PA Big Pike Delivery Meter (Pin 420245) - through 100% of PIP increases due to operational concerns; 3,086 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through 100% of PIP increases due to operational concerns; 7,732 Dths
· TRANSCO/TGP Rivervale New Jersey Ber Delivery Meter (Pin 420101) - through 100% of SIPss increases due to operational concerns; 3,822 Dths
SEGMENT RESTRICTIONS
· STA 25 (Segment 125 FH) - through 100% of IT increases due to nominations in excess of operational capacity; 4,544 Dths
· STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,346 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 277,895 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 114,909 Dths
· STA 321 (Segment 321 FH) - through 100% of PIP increases due to nominations in excess of operational capacity; 83,908 Dths
· STA 224 (Segment 224 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 105,619 Dths
· Z5 HC North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 314,661 Dths
· STA 245 (Segment 245 FH) - through 100% of PIP increases due to nominations in excess of operational capacity; 372,123 Dths
· STA 249 (Segment 249 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 284,625 Dths
· STA 254 (Segment 249 FH) - through approx 90% of SOP increases due to nominations in excess of operational capacity; 96,642 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 126,608 Dths
· STA 268 North (Segment 268 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 340 Dths
LINEPACK RESTRICTIONS
Payback OFF the pipe in all of Zones 4, 5 and 6 will not be scheduled until further notice. Payback in other areas of the system will continue to be evaluated at each and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.