Effective Intraday 2 Cycle (18:00) for the gas day of Thursday, December 19, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
METER RESTRICTIONS
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· Wright Receipt Meter (Pin 412181) - through approx 7% of IT increases due to nominations in excess of operational capacity; 4,104 Dths
SEGMENT RESTRICTIONS
· STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 257,895 Dths
· MLV 314 East (Segment 314 BH) - through approx 48% of SOP increases due to nominations in excess of operational capacity; 63,398 Dths
· STA 321 (Segment 321 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 203,378 Dths
· STA 325 (Segment 324 FH) - through 100% of SOP increases due to operational concerns; 108,536 Dths
· Z5hc North (Segment 299 FH) - through 100% of SIPss increases due to nominations in excess of operational capacity; 256,693 Dths
· STA 245 (Segment 245 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 331,473 Dths
· STA 249 (Segment 249 FH) - through approx 85% of SOP increases due to nominations in excess of operational capacity; 157,115 Dths
· STA 254 (Segment 249 FH) - through approx 91% of SOP increases due to nominations in excess of operational capacity; 181,412 Dths
· STA 261 Discharge East (Segment 261 FH) - through 100% of SIPsp increases due to nominations in excess of operational capacity; 104,612 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 163,817 Dths
· STA 268 North(Segment 268 FH) - through 100% of IT increases due to operational concerns; 242 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.