Effective Intraday 3 Cycle (22:00) for the gas day of Tuesday, November 19, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY ACTION ALERT FOR ALL OF ZONE 0, ZONE 1 ON THE 100 LINE, ALL OF ZONES 2, 3, 4 AND 5 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
SEGMENT RESTRICTIONS
· STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 10,000 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to operational concerns; 9,982 Dths
· Z5hc North (Segment 299 FH) - through approx 51% of SOP increases due to nominations in excess of operational capacity; 25,083 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will not accept nominations for FSAO injections at all storage fields.
Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.