Effective Intraday 1 Cycle (14:00) for the gas day of Friday, November 08, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONE 0, ZONE 1 ON THE 100 LINE, ALL OF ZONES 2, 3, 4, 5 AND 6 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPss increases due to operational concerns; 5,323 Dths
· Tres PAL/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SOP increases due to imbalance management quantity exceeded 60,712 Dths
· GULFSTH/TGP Coastal Bend LNG Wharton Delivery Meter (Pin 49524) - through 100% of SIPps increases due to operational concerns; 15,000 Dths
· ANR/TGP Greenville Intercon Delivery Meter (Pin 420941) - through 100% of SOP increases due to operational concerns; 23,600 Dths
· TRNSCO/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
SEGMENT RESTRICTIONS
· STA 860 (Segment 860 BH) - through 100% of SOP increases due to force majeure at STA 860; 10,000 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 260,380 Dths
· MLV 314 East (Segment 314 BH) - through approx 76% of SOP increases due to nominations in excess of operational capacity; 82,129 Dths
· STA 315 (Segment 315 BH) - through approx 50% of SOP increases due to nominations in excess of operational capacity; 108,474 Dths
· STA 321 (Segment 321 FH) - through approx 72% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 34,061 Dths
· Z5hc North (Segment 299 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 200,226 Dths
· STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 216,420 Dths
· STA 249 (Segment 249 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 117,487 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 124,648 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will not accept nominations for FSAO injections at all storage fields.
Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.