Effective Intraday 2 Cycle (18:00) for the gas day of Sunday, October 27, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONE 0, ZONE 1 ON THE 100 LINE, ALL OF ZONES 2, 3, 4, 5 AND 6 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· Westl CE/TGP Mississippi Transport Delivery Meter (Pin 420694) - through 100% of PAYBACK TGP increases due to nominations in excess of operational capacity; 3,756 Dths
SEGMENT RESTRICTIONS
· STA 860 South 800 Line (Segment 847 BH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 1,107 Dths
· STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 14,263 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 110,744 Dths
· MLV 314 East (Segment 314 BH) - through approx 97% of SOP increases due to nominations in excess of operational capacity; 144,889 Dths
· STA 321 (Segment 321 FH) - through approx 65% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 125,682 Dths
· Z5hc North (Segment 299 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 164,643 Dths
· STA 245 (Segment 245 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 220,018 Dths
· STA 249 (Segment 249 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 61,022 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 103,073 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will not accept nominations for FSAO injections at all storage fields.
Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.