Effective Evening Cycle (9:00) for the gas day of Thursday, October 24, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of PIP increases due to operational concerns; 5,008 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to operational concerns; 12,196 Dths
· Westl CE/TGP Mississippi Transport Delivery Meter (Pin 420694) - through approx 26% of PAYBACK T increases due to nominations in excess of operational capacity; 4,156 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 31% of SIPss increases due to nominations in excess of operational capacity; 24,575 Dths
SEGMENT RESTRICTIONS
· MLV 822 East (Segment 822 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 4,992 Dths
· STA 860 South 800 Line (Segment 847 BH) - through 100% of SIPsp increases due to scheduled maintenance and nominations in excess of operational capacity; 1,107 Dths
· STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP increases due to operational concerns; 30,000 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 254,182 Dths
· MLV 314 East (Segment 314 BH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 143,718 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 727,388 Dths
· Z5hc North (Segment 299 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 213,604 Dths
· STA 245 (Segment 245 FH) - through approx 63% of SOP increases due to nominations in excess of operational capacity; 194,027 Dths
· STA 249 (Segment 249 FH) - through approx 99% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 213,464 Dths
· MLV 273 (Segment 284 FH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 82,222 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will not accept nominations for FSAO injections at all storage fields.
Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.