Effective Timely Cycle (9:00) for the gas day of Monday, October 07, 2024 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 ON THE 500 LINE ONLY FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
OFO DAILY CRITICAL DAY 1 FOR ALL OF ZONES 4, 5 AND 6 FOR UNDER-TAKES OUT OF THE SYSTEM OR OVER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· TGP/SNG Bear Creek Injection Bienvi Delivery Meter (Pin 405367) - through 100% of SOP due to operational concerns; 10,000 Dths
· TRNSCO/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps due to operational concerns; 10 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 41% of SIPss due to nominations in excess of operational capacity; 46,435 Dths
SEGMENT RESTRICTIONS
· STA 834 (Segment 834 BH) - through approx 36% of SA due to nominations in excess of operational capacity; 26,956 Dths
· STA 87 South 800 Line (Segment 860 BH) - through 100% of SOP due to operational concerns; 45,000 Dths
· STA 110 South (Segment 187 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 9,982 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 254,182 Dths
· MLV 314 East (Segment 314 BH) - through approx 91% of SOP due to nominations in excess of operational capacity; 262,912 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP due to nominations in excess of operational capacity; 593,563 Dths
· STA 317 (Segment 317 BH) - through 100% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 108,456 Dths
· STA 321 (Segment 321 FH) - through approx 52% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 456,820 Dths
· STA 325 (Segment 324 FH) - through approx 34% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 103,581 Dths
· Z5hc North (Segment 299 FH) - through approx 73% of SOP due to nominations in excess of operational capacity; 524,750 Dths
· STA 245 (Segment 245 FH) - through approx 86% of SOP due to scheduled maintenance and nominations in excess of operational capacity; 699,892 Dths
· STA 249 (Segment 249 FH) - through approx 27% of SOP due to nominations in excess of operational capacity; 117,743 Dths
· MLV 273 (Segment 284 FH) - through approx 94% of SOP due to nominations in excess of operational capacity; 188,502 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not accept nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will not accept nominations for FSAO injections at all storage fields.
Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
Additionally, no Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.