Project Updates
“***MLV 117-3 to MLV 118-3: Special Permit Pipe Replacement
--8/18/26 through 9/12/26: This project will require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations.
***
Date Change, Previously scheduled 8/18/26 to 9/11/26.
………………………………
***MLV 119-2 to MLV 119-2A: Special Permit Pipe Replacement
***MLV 329AS-1 to MLV 329AD-1: Valve Replacement - MLV 329-1 --CANCELLED: This project will require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations. The meters listed may be constrained or shut in during the project. 420226 PSEG/TGP RAMSEY NJ BERGEN *** Date Change, Previously scheduled 9/9/26 to 10/9/26. ………………………………
”
If you have any questions, please contact your Scheduler.