EXCESSIVE HOURLY TAKES WARNING FOR ALL AREAS EAST OF STA 249 ON THE 200 LINE EFFECTIVE 12-2-2025
Effective immediately for the Gas Day of Tuesday, December 2, 2025, and until further notice, Tennessee Gas Pipeline, LLC (“Tennessee”) has limited operational flexibility to manage excessive hourly imbalance over-takes for all areas East of STA 249 on the 200 Line.
Tennessee requires your compliance with this notice to avoid the necessity of taking further actions including utilizing contract or meter specific Hourly Operational Flow Orders or flow control to maintain operational integrity.
THIS EXCESS HOURLY TAKES WARNING WILL REMAIN IN EFFECT UNTIL FURTHER NOTICE.
TENNESSEE WILL INFORM CUSTOMERS BY EBB WHEN THIS EXCESS HOURLY TAKES WARNING WILL BE LIFTED.
Tennessee would like to remind all operators/agents of power plants directly connected to TGP of certain parameters of FERC Order 698 requirements. Tennessee requires that all power plant operators submit burn profiles and nominations prior to gas flow. Due to very limited flexibility, power plant operators are encouraged to burn ratably based on scheduled volumes in order to avoid the necessity of taking further actions. The burn profiles should be sent to TGPGasControl@Kindermorgan.com. The latest burn profile template can be found by accessing the Tennessee web site and following the steps below.
https://pipeportal.kindermorgan.com/PortalUI/DefaultKM.aspx?TSP=TGPD
Customer Information
Presentations
PowerPlantBurnProfile.xls
Please contact your Scheduler if you have any questions.
Your session will expire in . Click OK to renew your session.