Effective Evening Cycle (9:00) for the gas day of Saturday, November 15, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
NONE
SEGMENT RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 50,781 Dths
· STA 823 Muskrat Line (Segment 509 BH) - through 100% of SOP increases due to operational concerns; 5,006 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 343,132 Dths
· MLV 314 East (Segment 314 BH) - through approx 99% of SOP increases due to nominations in excess of operational capacity; 260,950 Dths
· STA 315 (Segment 315 BH) - through approx 74% of SOP increases due to nominations in excess of operational capacity; 187,609 Dths
· STA 317 (Segment 317 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 61,041 Dths
· STA 321 (Segment 321 FH) - through approx 41% of SOP increases due to nominations in excess of operational capacity; 68,839 Dths
· STA 325 (Segment 324 FH) - through approx 28% of SOP increases due to nominations in excess of operational capacity; 44,399 Dths
· MLV 330 (Segment 324 FH) - through approx 77% of SOP increases due to nominations in excess of operational capacity; 87,867 Dths
· STA 224 (Segment 224 FH) - through approx 84% of SOP increases due to nominations in excess of operational capacity; 64,558 Dths
· STA 313Hcg - Z4 Hc (Segment 399 FH) - through approx 79% of SOP increases due to nominations in excess of operational capacity; 179,884 Dths
· Z5hc North (Segment 299 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 252,737 Dths
· STA 245 (Segment 245 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 405,688 Dths
· STA 249 (Segment 249 FH) - through approx 98% of SOP increases due to nominations in excess of operational capacity; 278,264 Dths
· STA 254 (Segment 249 FH) - through approx 19% of SOP increases due to nominations in excess of operational capacity; 15,787 Dths
· STA 261 Discharge East (Segment 261 FH) - through approx 95% of SOP increases due to nominations in excess of operational capacity; 114,464 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 230,437 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.