-Primary impact restrictions may be necessary
TGP - Outage Impact Report
-Major impact restrictions may be necessary
Seven Day Forecast (updated 11/13/25)
-Minor impact restrictions may be necessary depending on flow conditions
-Little to no impact, though minor outages may cause incremental reductions
Station / Seg
Est Nominal
Operating Capacity (Thousand Dth)
Monday
(11/17)
Tuesday
(11/18)
Wednesday
(11/19)
Thursday
(11/20)
Friday
(11/21)
Saturday
(11/22)
Sunday
(11/23)
Primary Outage(s) that may Impact Throughput
Est. Operational Capacity (Operational Impact) - Thousand Dth
Station 409A (Alamo) (segment 492 FH)
295
145
(150)
MLV 409A-901 to MLV 409A-902: Pig Run - Cleaning 11/18/25 (M)
(11/18/2025)
MLV 409A-901 to MLV 409A-902: Pig Run - MFL-A 11/19/25 (M) (11/19/2025)
Station 409 (Donna Line) (segment 490 FH)
585
Station 1
(segment 101 BH)
438
418
(28)
MLV 1-2BL to MLV 1-2A: GCX Expansion Hot Tap/Tie in (M) (11/18/2025 - 11/21/2025)
Station 9
(segment 109 BH)
1,066
Station 17
(segment 117 FH)
1,143
1130
(13)
MLV 17-1D to MLV 18-1: Anomaly Remediation (11/3/2025 - 11/21/2025)
Station 25
(segment 125 FH)
1,101
1085
(16)
Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)
Station 40 South
(segment 132 FH)
1,299
1090
(209)
MLV 36-1LA to MLV 40-1S: Pig Run - Maintenance (11/17/2025)
Station 47
(segment 143 FH)
1,354
890
(464)
MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-4A to MLV 48-4: Pipe Replacement (M) (11/13/2025 - 11/24/2025)
MLV 53-3BR to MLV 54-3BL: HydroTest (11/12/2025 - 12/16/2025)
Sta 54: Unit 6B - Power Overhaul (10/1/2025 - 11/24/2025) Sta 54: Unit 8B - Power Overhaul (10/1/2025 - 11/24/2025)
Station 63
(segment 163 FH)
1,287
1135
(152)
MLV 65-2 to MLV 66-2: Immediate Anomaly Remediation (11/17/2025 - 11/30/2025)
MLV 66-2 to MLV 67-2: Immediate Anomaly Remediation (11/17/2025 - 11/30/2025)
Station 823
(segment 823 BH)
759
Station 834
(segment 834 BH)
733
720
Sta 834: Unit 6A - Overhaul (3/3/2025 - 1/2/2026)
Station 527
(segment 527 BH)
2,477
2300
(177)
Sta 529: Solar Inspection & Safety Devices (11/18/2025 - 11/20/2025)
Station 534 South of Pool (segment 530 BH)
1,632
1294
(338)
Sta 530: Unit 1A - Bearings (8/25/2025 - 3/31/2026) Sta 530: Unit 2A - Bearings (8/26/2025 - 12/31/2025)
Sta 530: Unit 3A - Crankshaft Replacement (6/9/2025 - 12/31/2026) Sta 530: Unit 5A - Top-End Overhaul (6/9/2025 - 12/31/2026)
Sta 530: Unit 6A - Bearings (10/6/2025 - 3/31/2026) Sta 530: Unit 7A - Bearings (10/6/2025 - 3/31/2026)
Sta 530: Unit 8A - Power Cylinders (9/23/2025 - 12/31/2025)
Sta 534: Unit 6A - Piston Liner & Unloader Replacements (3/25/2025 - 12/31/2025)
Sta 534: Unit 7A - Piston / Liner (5/20/2025 - 12/5/2025)
Station 542
(segment 539 BH)
1,905
1825
(80)
1870
(35)
Sta 542: Unit 2A - Crankcase Pressure Investigation (11/11/2025 - 11/28/2025) Sta 542: Unit 4A - Cooler Fan (11/17/2025 - 11/18/2025)
MLV 548
(segment 542 BH)
1,771
1735
(36)
Sta 546: Unit 4A - Engine and Compressor Overhaul (11/3/2025 - 12/12/2025) Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/31/2025)
Station 860
(segment 548 BH)
1,697
1680
(17)
Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025)
Station 860 North (Segment 860 BH)
2,028
1715
(313)
1710
(318)
2000
MLV 565-1 to MLV 559-1: Pig Run - Brush / Gauige 11/17 (11/17/2025) MLV 565-1 to MLV 559-1: Pig Run - CLP / IMU 11/18 (11/18/2025) MLV 565-1 to MLV 559-1: Pig Run - MFL-C 11/20 (11/20/2025)
Sta 860: Unit 1A - Aftercooler Jacket Water Inspection (6/17/2025 - 12/31/2026)
Sta 860: Unit 1C - Solar Engine Maintenance (11/18/2025) Sta 860: Unit 2C - Solar Engine Maintenance (11/19/2025)
Station 110
(segment 187 BH)
(south thru Kentucky)
2,775
2460
(315)
MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement (M) (11/1/2025 -
11/26/2025)
MLV 90-3 to MLV 91-3: HDD River Crossing Replacement (10/23/2025 - 12/5/2025)
Sta 106 Clay City: Upgrade B Building Jacket Water System (11/14/2025 - 12/5/2025)
Sta 87: Unit 2E - Turbocharger Replacement (10/27/2025 - 12/12/2025) Sta 871: Unit 2A - Turbo (11/6/2025 - 11/26/2025)
Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026)
Station 114
(segment 114 BH)
948
Station 204
(Segment 204 BH)
1,895
1732
(163)
1459
(436)
1460
(435)
MLV 213-2A to MLV 214-2: Special Permit Replacement (10/9/2025 - 11/19/2025)
MLV 219-4 to MLV 214-4: Pig Run - EMAT 11/20/25 (M) (11/20/2025) MLV 219-4 to MLV 214-4: Pig Run - MFL-C 11/18/25 (M) (11/18/2025)
Sta 209: Unit 12A - P3L pull piston and inspect rings and cylinder (11/17/2025 -
11/20/2025)
Station 245
(segment 245 FH)
1,063
1025
(38)
Sta 241: Unit 1B - Compressor Valve (11/18/2025 - 11/20/2025) Sta 241: Unit 3A - Ignition System (11/12/2025 - 11/28/2025)
Station 261 Discharge East (segment 261 FH)
1,045
Station 267 South (segment 266 FH)
503
346
(157)
Sta 267: Bldg A Controls Upgrade (9/2/2025 - 11/26/2025)
Station 307
(segment 307 BH)
1,202
1110
(92)
Sta 307: Unit 5A - Engine Maintenance (11/17/2025 - 11/20/2025)
Station 315
(segment 315 BH)
1,915
MLV 324
(segment 324 FH)
1,885
Station 405 HC Line (segment 299 FH)
827
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses.
Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.
The impacts sheet are based on steady-state hydraulic models assuming recent operating flows, conditions, and various unit outages.
November 2025 (updated 11/13/25)
Station # / Lateral
Est Nominal Operating Capacity (Thousand Dth)
Week 1
(11/3 - 11/9)
Week 2
(11/10 - 11/16)
Week 3
(11/17 - 11/23)
Week 4
(11/24 - 11/30)
Primary Outage(s)
MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025) MLV 47-3A to MLV 48-3: Pipe Replacement (11/25/2025 - 12/10/2025)
MLV 47-4A to MLV 48-4: Pipe Replacement (M) (11/13/2025 - 11/24/2025) MLV 53-3BR to MLV 54-3BL: HydroTest (11/12/2025 - 12/16/2025)
(477)
Sta 527: Units 1B & 2B - Replace Witch's Hat (11/24/2025 - 11/25/2025)
Sta 542: Unit 2A - Crankcase Pressure Investigation (11/11/2025 - 11/28/2025)
MLV 108-2 to MLV 109-2: Special Permit Pipe Replacement (M) (11/1/2025 - 11/26/2025)
December 2025 (updated 11/13/25)
(12/1 - 12/7)
(12/8 - 12/14)
(12/15 - 12/21)
(12/22 - 12/28)
910
(389)
1286
MLV 32-2D TO MLV 40-2S: Pig Runs - Maintenance (12/2/2025) MLV 32-3D to MLV 40-3S: Pig Runs - Maintenance (12/10/2025)
Station 40 KN South (segment 501 FH)
285
100
(185)
Sta 500-1 to Sta 823 (MLV 507-1): Pig Run - Maintenance (M) (12/16/2025)
895
(459)
950
(404)
1349
(5)
Sta 47: Unit 1D - Flush & Clean Cooling Systems (12/1/2025 - 12/6/2025) Sta 47: Unit 2D - Flush & Clean Cooling Systems (12/1/2025 - 12/6/2025)
Station 847
(segment 847 BH)
338
200
(138)
MLV 856-1 to MLV 860-1: Pig Runs - Cal / IMU 12/9/25 (12/9/2025)
MLV 856-1 to MLV 860-1: Pig Runs - Cleaning / Gauge 12/4/25 (12/4/2025) MLV 856-1 to MLV 860-1: Pig Runs - MFL-C 12/11/25 (12/11/2025)
1400
(232)
1750
(21)
Sta 550: Unit 2A - Compressor Overhaul (8/25/2025 - 12/5/2025) Sta 550: Unit 3A - Turbocharger Exchange (12/8/2025 - 12/19/2025)
1620
(408)
MLV 559-2 to MLV 565-2: Pig Run - Caliper (12/11/2025) MLV 559-2 to MLV 565-2: Pig Run - EMAT (12/18/2025) MLV 559-2 to MLV 565-2: Pig Run - Gauge (12/9/2025) MLV 559-2 to MLV 565-2: Pig Run - MFL (12/16/2025)
2560
(215)
2600
(175)
2645
(130)
Sta 87: Unit 2E - Turbocharger Replacement (10/27/2025 - 12/12/2025) Sta 871: Unit 3A - Engine Crankshaft Inspection (8/22/2025 - 1/30/2026) Sta 96: Unit 1D - Compressor Valves (12/1/2025 - 12/12/2025)
1722
(173)
MLV 204-2 to MLV 200-2: Pig Runs - EMAT 12/18/25 (M) (12/18/2025) MLV 204-2 to MLV 200-2: Pig Runs - MFL-C 12/16/25 (M) (12/16/2025)
Station 224
(segment 224 FH)
399
205
(194)
Sta 229: Automation Upgrade for Air Compressor (M) (12/8/2025 - 12/10/2025)
January 2026 (updated 11/13/25)
(12/29 - 1/4)
(1/5 - 1/11)
(1/12 - 1/18)
(1/19 - 1/25)
Week 5
(1/26 - 2/1)
MLV 26-1 Relocation: Highway 59 Widening (1/19/2026 - 2/19/2026) Sta 25: Unit 1C - VFD Replacement (7/16/2025 - 10/31/2026)
MLV 47-1A to MLV 48-1: Class Change (9/1/2025 - 12/31/2025)
1610
(22)
Sta 546: Unit 7A - Metal in Oil (7/14/2025 - 12/31/2025)
(south thru
Kentucky)
2535
(240)
Sta 871: Unit 1A - 3Q Engine Inspection (12/31/2025) Sta 871: Unit 2A - 3Q Engine Inspection (12/31/2025)
785
Sta 114: Unit 1D - Solar Turbine Inspection (1/13/2026)
This document is updated on a weekly basis and outage schedules/impacts are subject to change as the week progresses. Dates posted on DART should be deemed correct in the event of conflicts between DART posted dates and dates on this report.