Effective Evening Cycle (9:00) for the gas day of Monday, May 26, 2025 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 SYSTEM WIDE (EXCLUDING AREAS SOUTH OF STA 1 AND THE 500 LINE) FOR OVER-DELIVERIES INTO THE SYSTEM OR UNDER-TAKES OUT OF THE SYSTEM FOR ALL BALANCING PARTIES
METER RESTRICTIONS
· GULFSTH/TGP Kiln Miss Exchange Hanc Delivery Meter (Pin 420383) - through 100% of SOP increases due to imbalance management quantity exceeded; 100 Dths
· KMTEJAS/TGP Jackson (Ganado) Delivery Meter (Pin 49803) - through 100% of IT increases due to nominations in excess of operational capacity; 1,489 Dths
· Pine PRA/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through 100% of SOP increases due to operational concerns; 5,000 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 69% of SIPss increases due to nominations in excess of operational capacity; 35,012 Dths
SEGMENT RESTRICTIONS
· STA 860 (Segment 860 BH) - through 100% of SIPsp increases due to force majeure at STA 860; 2,297 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 428,714 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 327,590 Dths
· STA 315 (Segment 315 BH) - through approx 89% of SOP increases due to nominations in excess of operational capacity; 266,835 Dths
· STA 321 (Segment 321 FH) - through approx 61% of SOP increases due to nominations in excess of operational capacity; 207,553 Dths
· MLV 330 (Segment 324 FH) - through approx 35% of SOP increases due to nominations in excess of operational capacity; 39,537 Dths
· STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 367,798 Dths
· STA 249 (Segment 249 FH) - through approx 38% of SOP increases due to nominations in excess of operational capacity; 58,552 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 167,059 Dths
LINEPACK RESTRICTIONS
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PALD service
· No Parks or Loan Paybacks under Rate Schedule PAL utilizing the PAL-AO service
· Paybacks will be evaluated at each cycle and scheduled only if operationally feasible
STORAGE RESTRICTIONS
· No Authorized Overrun Injections Services under Rate Schedule FS-AO as well as No Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at the following storage fields:
· Northern MA (460018) storage field
· Portland MA (460025) storage field
· Portland PA (460020) storage field
· Bear Creek PA (460017) storage field
· No Interruptible Storage Injection Services under Rate Schedule IS at the following storage fields:
· Northern MA (460018) storage field (IS-MA)
· Bear Creek PA (460017) storage field (IS-PA)
**PLEASE NOTE MAXIMUM HOURLY ENTITLEMENTS ("MHE") AND/OR ELAPSED PRO RATA SCHEDULED QUANTITIES ("EPSQ") WILL BE REVIEWED AND MAY BE ENFORCED AT ANY METER DURING INTRADAY OR HOURLY CYCLES.
**FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.