"***MLV 115-3 to MLV 116-3: Anomaly Remediation
--5/5/25 through 5/18/25: This project may require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations. The meter listed may be constrained or shut in during the project. Potential in the path restrictions may be at risk.
49274 CRANBERY/TGP BEECHFORK DELIVERY WAY
***
Date Change, Previously scheduled 4/14/25 to 4/27/25.
………………………………"
"***MLV 115-2A to MLV 116-2: Anomaly Remediation
--5/5/25 through 5/10/25: This project may require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations. Potential in the path restrictions may be at risk.
Date Change, Previously scheduled 4/7/25 to 4/13/25.
"***MLV 116-3 to MLV 117-3: Anomaly Remediation
--5/5/25 through 5/18/25: This project will require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
***Added
"***MLV 117-3 to MLV 118-3: Anomaly Remediation
--5/19/25 through 5/25/25: This project will require taking the pipeline section out of service which could limit throughput and result in restrictions based on customer nominations. Potential out of path restrictions may be at risk.
If you have any questions, please contact your Scheduler.