Effective Evening Cycle (9:00) for the gas day of October 01, 2023 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ZONES L AND 1 FOR 500 LEG ONLY FOR OVER-TAKES FROM THE SYSTEM OR UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES and MONTHLY OFO CRITICAL DAY 1 FOR ALL OF ZONE 4 FOR LMS-PAs AND SAs ACTING AS BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SIPsp increases receipts due to displacement gas unavailable for backhaul; 119,963 Dths
· Tres Pal/TGP Tres Palacios Storage: Delivery Meter (Pin 421055) - through 100% of SIPps increases due to operational concerns; 22,163 Dths
· Gulfsth/TGP Coastal Bend Lng Wharto Delivery Meter (Pin 49524) - through 100% of SIPss increases due to operational concerns; 24,264 Dths
· Acadian/TGP Indian Bayou: Dip 510B- Delivery Meter (Pin 421056) - through 100% of SOP increases due to imbalance management quantity exceeded; 2,000 Dths
· Pine Pra/TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 90% of SOP increases due to operational concerns; 66,570 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to operational concerns; 7,430 Dths
· STA 860 (Segment 860 BH) - through 100% of PIP increases due to force majeure at STA 860; 9,054 Dths
· Gulfsth/TGP Petal Storage Field For Delivery Meter (Pin 420797) - through approx 4% of SIPps increases due to operational concerns; 3,993 Dths
· Trnsco/TGP Heidelberg Missisippi Ja Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· STA 542 (Segment 542 BH) - through 100% of SOP increases due to operational concerns; 4,950 Dths
· STA 114 East (Segment 114 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 66,818 Dths
· STA 110 East (Segment 111 BH) - through 100% of SOP increases due to operational concerns; 48,703 Dths
· STA 204 (Segment 204 BH) - through approx 88% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 249,332 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 140,531 Dths
· MLV 314 East (Segment 314 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 85,351 Dths
· STA 315 (Segment 315 BH) - through approx 37% of SOP increases due to emergent repair at STA 315 Unit 2A; 40,433 Dths
· STA 321 (Segment 321 FH) - through approx 83% of SOP increases due to nominations in excess of operational capacity; 308,629 Dths
· STA 325 (Segment 324 FH) - through approx 58% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 32,191 Dths
· Z5HC North (Segment 299 FH) - through approx 96% of SOP increases due to nominations in excess of operational capacity; 191,626 Dths
· STA 245 (Segment 245 FH) - through approx 77% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 194,903 Dths
· MLV 273 (Segment 284 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 123,776 Dths
LINEPACK RESTRICTIONS
Payback will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
Tennessee will not schedule nominations for Authorized Overrun Injection Services (FS-AO) or Authorized Overrun Injections in excess of Maximum Daily Injection Quantity (MDIQ) but below Maximum Daily Withdrawal Quantity (MDWQ) at Northern MA (460018), Portland MA (460025), Portland PA (460020) or Bear Creek (460017) until further notice. Tennessee will not schedule nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-MA) at the Northern MA (460018) storage field and Tennessee will not schedule nominations for Interruptible Storage Injection Services under Rate Schedule IS (IS-PA) at the Bear Creek PA (460017) storage field.
Tennessee will NOT approve any transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the FS-PA storage service only with partner approvals.
No Parks or Loan Paybacks under Rate Schedule PAL will be allowed utilizing the PAL-D or PAL-AO services system wide.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.