TSP/TSP Name:  1939164-TENNESSEE GAS PIPELINE Critical: Y
Notice Type Desc (1):  PIPELINE CONDITIONS Notice Type Desc (2):  CURRENT PIPELINE CONDITIONS
Notice Eff Date/Time:  09/08/2022 3:46:50PM Notice End Date/Time:  09/09/2022 9:00:00am
Post Date/Time:  9/8/2022 3:46:50 PM Notice ID: 384213
Reqrd Rsp:  1 Rsp Date:  09/08/2022
Notice Stat Desc:  INITIATE Prior Notice: 
Subject:  RESTRICTIONS FOR 09-08-2022 ID2
Notice Text:

Effective Intraday 2 Cycle (18:00) for the gas day of September 08, 2022 Tennessee restricted the following:

OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS

OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES

MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM

RESTRICTIONS

·         Whistle/TGP Whistler Receipt Nuece Receipt Meter (Pin 54847) - through 100% of SOP increases due to operational concerns; 630 Dths

·         Net Mexi/TGP Gillrina Road Nueces Receipt Meter (Pin 47799) - through 100% of SA increases due to operational concerns; 10,179 Dths

·         STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 37,017 Dths

·         Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 95% of SOP increases due to imbalance management quantity exceeded; 99,440 Dths

·         STA 834 (Segment 834 BH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 5,889 Dths

·         Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths

·         TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to operational concerns; 127 Dths

·         MLV 548 (Segment 542 BH) - through 100% of SA increases due to scheduled maintenance and nominations in excess of operational capacity; 7,000 Dths

·         Atmos KY/TGP Simpson Delivery Meter (Pin 421000) - through 100% of SIPss increases due to nominations in excess of operational capacity; 78 Dths

·         STA 307 (Segment 307 BH) - through 100% of SOP increases due to the force majeure at MLV 309 to MLV 310; 55,000 Dths

·         MLV 314 East (Segment 314 BH) - through approx 71% of SOP increases due to nominations in excess of operational capacity; 41,938 Dths

·         AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 18% of SOP increases due to nominations in excess of operational capacity; 14,955 Dths

·         MLV 330 (Segment 324 FH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 121,704 Dths

·         STA 245 (Segment 245 FH) - through approx 67% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 86,189 Dths

·         MLV 273 (Segment 284 FH) - through approx 81% of SOP increases due to nominations in excess of operational capacity; 39,496 Dths

LINEPACK RESTRICTIONS

No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or South of STA 542 on the 500 until further notice.  PALD and PALAO nominations OFF the system will not be scheduled in these areas.  Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.

STORAGE RESTRICTIONS

NONE

**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.

**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.

If you have any questions, please contact your Scheduler.

 

..