Effective Intraday 2 Cycle (18:00) for the gas day of August 25, 2022 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR SOUTH OF STA 1 FOR OVER-TAKES FROM THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
MONTHLY OFO CRITICAL DAY 1 FOR ZONE 4 FOR ALL LMS-PA AND SA BALANCING PARTIES FOR OVER-DELIVERIES INTO THE SYSTEM
RESTRICTIONS
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to operational concerns; 8,652 Dths
· Pine Prairie /TGP Pine Prairie North Rap Delivery Meter (Pin 421043) - through approx 99% of SOP increases due to imbalance management quantity exceeded; 111,385 Dths
· STA 834 (Segment 834 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 1,275 Dths
· TGP/SNG Toca Exchange St Bernard Delivery Meter (Pin 420556) - through 100% of SOP increases due to operational concerns; 3 Dths
· Leaf/TGP Jasper County: Rip 538 2 5 Delivery Meter (Pin 412789) - through 100% of SOP increases due to operational concerns; 17,233 Dths
· Transco/TGP Heidelberg Mississippi Delivery Meter (Pin 420291) - through 100% of SIPps increases due to operational concerns; 10 Dths
· TGP/SNG Rose Hill Miss Clarke Delivery Meter (Pin 420546) - through 100% of SIPps increases due to nominations in excess of operational capacity; 692 Dths
· MLV 548 (Segment 542 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· STA 307 (Segment 307 BH) - through 100% of SOP increases due to the force majeure at MLV 309 to MLV 310; 91,414 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 23,130 Dths
· STA 321 (Segment 321 FH) - through approx 94% of SOP increases due to nominations in excess of operational capacity; 235,700 Dths
· AGT/TGP Mahwah New Jersey Bergen Delivery Meter (Pin 420207) - through approx 16% of SOP increases due to nominations in excess of operational capacity; 10,644 Dths
· Z5HC North (Segment 299 FH) - through approx 38% of SOP increases due to nominations in excess of operational capacity; 38,424 Dths
· STA 245 (Segment 245 FH) - through approx 92% of SOP increases due to nominations in excess of operational capacity; 179,327 Dths
· MLV 273 (Segment 284 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 42,209 Dths
LINEPACK RESTRICTIONS
No Payback FROM the pipe will be scheduled South of STA 1 in South Texas or South of STA 542 on the 500 until further notice. PALD and PALAO nominations OFF the system will not be scheduled in these areas. Additionally, Payback system wide will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
NONE
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.