Effective Intraday 2 Cycle (18:00) for the gas day of September 13, 2021 Tennessee restricted the following:
OPERATIONAL FLOW ORDERS (OFO) AND IMBALANCE WARNINGS
OFO DAILY CRITICAL DAY 1 FOR ALL AREAS SOUTH OF STA 9 FOR OVER-TAKES OUT OF THE SYSTEM AND UNDER-DELIVERIES INTO THE SYSTEM FOR ALL BALANCING PARTIES
OFO MONTHLY CRITICAL DAY 1 FOR ALL OF ZONE 4 FOR OVER-DELIVERIES INTO THE SYSTEM FOR LMPA AND SA BALANCING PARTIES
RESTRICTIONS
· STA 1 (Segment 101 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 29,303 Dths
· STA 823 (Segment 823 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 95,454 Dths
· STA 834 (Segment 834 BH) - through approx 38% of SOP increases due to nominations in excess of operational capacity; 12,203 Dths
· STA 114 East (Segment 114 BH) - through 100% of PIP increases due to scheduled maintenance and nominations in excess of operational capacity; 1,595 Dths
· STA 204 (Segment 204 BH) - through 100% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 10,000 Dths
· MLV 217 (Segment 217 BH) - through 100% of SOP increases due to operational concerns; 17,004 Dths
· MLV 314 East (Segment 314 BH) - through 100% of SOP increases due to nominations in excess of operational capacity; 9,994 Dths
· STA 315 (Segment 315 BH) - through approx 80% of SOP increases due to nominations in excess of operational capacity; 49,659 Dths
· STA 321 (Segment 321 FH) - through 100% of SOP increases due to nominations in excess of operational capacity; 24,036 Dths
· STA 245 (Segment 245 FH) - through approx 83% of SOP increases due to scheduled maintenance and nominations in excess of operational capacity; 162,689 Dths
· MLV 273 (Segment 284 FH) - through approx 93% of SOP increases due to nominations in excess of operational capacity; 6,095 Dths
LINEPACK RESTRICTIONS
Payback nominations FROM the pipe in all areas South of STA 9 as well as Payback nominations TO the pipe in Zone 4 will be evaluated at each cycle and scheduled only if operationally feasible.
STORAGE RESTRICTIONS
No transfers from accounts at TGP Bear Creek Storage to SNG Bear Creek Storage (460017) (IS-PA, FS-PA) until further notice. Transfers into TGP Bear Creek Storage (460017) from SNG Bear Creek Storage will be allowed under the (IS-PA, FS-PA) storage services with partner approvals.
**PLEASE NOTE THAT FINAL VOLUMES MAY CHANGE DUE TO SYSTEM BALANCING AND/OR CONFIRMATION REDUCTIONS.
**THE OUTAGE AND MAINTENANCE SCHEDULE IS AVAILABLE IN EXCEL SPREADSHEET AND ADOBE FORMATS WHICH MAY BE ACCESSED VIA A HYPERLINK UNDER NOTICES/PLANNED SERVICE OUTAGES.
If you have any questions, please contact your Scheduler.